Calder Bay Complex
U21
11/10/26 – 12/10/26
Total equipment
185
click to see the wall chart
Closed out
12
7% incl. 1 removed from scope
Open RRs
8
Discovery
55%
335 / 607 inspections · 27 / 95 equipment fully inspected
Awaiting a decision (3)
RR-009-E-2112B · E-2112B · Tube Bundle
Localized pitting at bottom head
RR-010-E-2103B · E-2103B · Floating Head
Tube wall loss, IRIS
RR-011-8"-P-2138-C1 · 8"-P-2138-C1
Nozzle weld crack indication
Turnaround at a glance
- Closed out126%
- Removed from scope11%
Progress by asset type
Drums
30
Complete or removed
13%
3 Closed out26 open2 RRs
1 removed from scope
Discovery54% · 81 / 150 boxes
6 / 30 equipment cleared14 in progress3 not started7 delayed
View wall chart →
Towers
8
Closed out
25%
2 Closed out6 open0 RRs
RRs written vs closed
Exchangers1 / 7 closed · 2 deferred
Drums0 / 2 closed
Heaters1 / 1 closed
PSV Pull0 / 1 closed
Pipe & Valves0 / 1 closed
Outstanding RRs
All RRs →Still outstanding
Drums · 26
| D-2110 | Vertical vessel | Repair |
| D-2113 | Horizontal vessel | In progress |
| D-2116 | Horizontal vessel with boot | In progress |
| D-2119 | Vertical vessel | In progress |
| D-2122 | Vertical vessel | In progress |
| D-2125 | Horizontal vessel with boot | In progress |
| D-2128 | Horizontal vessel with boot |