Calder Bay Complex · U21
Towers
8 in scope · 2 closed out · 0 open RRs
8 of 8 items · drag a column edge to resize
| Equip # | Equipment Name | Work Order | Description | Progress | Scope | Status | Internal Visual | External Visual | UTT | PAUT/UTSW | Flanges VI | Final QA | Repair Recommendation (RR) | Repair Complete | Comments |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| T-2101 | Atmospheric Tower | WO-48473 | 36 trays | Internal VI trays + shell, UTT, PAUT welds | Open | In progress. OS 11/22 top half complete | ● | ● | ● | ● | ○︎ | · | ○︎ | ○︎ | |
| T-2102 | Naphtha Stripper | WO-48780 | 36 trays | Closed out | Internal VI trays + shell, UTT, PAUT welds | Boxed up | KJ 11/11 | PN 11/13 | MF 11/16 | DP 11/17 Minor general corrosion, within allowance | OS 11/19 No cracking found | CV 11/22 | · | ○︎ | ○︎ |
| T-2103 | Kerosene Stripper | WO-48598 | 42 trays | Internal VI trays + shell, UTT, PAUT welds | Ready for inspection | CV 11/11 | CV 11/12 | WD 11/14 Light scale, no pitting | In progress. OS 11/22 about half done | ● | ○︎ | · | ○︎ | ○︎ | |
| T-2104 | Diesel Stripper | WO-48894 | 30 trays | Internal VI trays + shell, UTT, PAUT welds | Cleaned | DP 11/12 | RC 11/14 | PN 11/14 | Delayed. Waiting on scaffold | ● | ○︎ | · | ○︎ | ○︎ | |
| T-2105 | Debutanizer | WO-48389 | 36 trays | Internal VI trays + shell, UTT, PAUT welds | Cleaned | DP 11/12 | PN 11/12 Light scale, no pitting | RC 11/14 No cracking found | Delayed. Delayed | ● | ○︎ | · | ○︎ | ○︎ | |