Rolling log
20 entriesDwayne P.of 248
| Inspection details | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| 5/6/26 | Days | Dwayne P. | Exchangers | E-1402A Overhead Condenser | Shell | Final QA complete | — | — | — | — | |
| 5/6/26 | Days | Dwayne P. | Drums | D-1425 Desalter | — | Final QA complete | — | — | — | — | |
| 5/5/26 | Days | Dwayne P. | Exchangers | E-1407A Diesel Product Cooler | Shell | Final QA complete | — | — | — | — | |
| 5/5/26 | Days | Dwayne P. | PSV Pull | PSV-14310 | — | PSV Installed complete | — | — | — | — | |
| 5/3/26 | Days | Dwayne P. | Exchangers | E-1405A Reboiler | Floating Head | Final QA complete | — | — | — | — | |
| 4/27/26 | Days | Dwayne P. | Exchangers | E-1401A Crude / Diesel Exchanger | Tube Bundle | ECT/RFT/IRIS complete | — | — | — | — | |
| 4/25/26 | Days | Dwayne P. | Exchangers | E-1402A Overhead Condenser | Tube Bundle | ECT/RFT/IRIS complete | — | — | — | — | |
| 4/23/26 | Days | Dwayne P. | PSV Pull | PSV-14318 | — | Inlet Piping VT complete | — | — | — | — | |
| 4/21/26 | Days | Dwayne P. | PSV Pull | PSV-14306 | — | Inlet Piping VT complete | — | — | — | — | |
| 4/21/26 | Days | Dwayne P. | Exchangers | E-1402A Overhead Condenser | Tube Bundle | Flanges VI complete | — | — | — | — | |
| 4/20/26 | Days | Dwayne P. | Drums | D-1440 Compressor Suction KO | — | UTT complete. Gaskets surfaces good | — | — | — | — | |
| 4/19/26 | Days | Dwayne P. | Exchangers | E-1407A Diesel Product Cooler | Channel (Bonnet) | Flanges VI complete | — | — | — | — | |
| 4/16/26 | Days | Dwayne P. | Exchangers | E-1407A Diesel Product Cooler | Shell | VI complete | — | — | — | — | |
| 4/15/26 | Days | Dwayne P. | Exchangers | E-1406B Trim Cooler | Channel (Bonnet) | VI complete | — | — | — | — | |
| 4/15/26 | Days | Dwayne P. | Drums | D-1437 Amine Flash Drum | — | Internal Visual complete. Light scale, no pitting | — | — | — | — | |
| 4/15/26 | Days | Dwayne P. | Exchangers | E-1401A Crude / Diesel Exchanger | Floating Head | VI complete | — | — | — | — | |
| 4/13/26 | Days | Dwayne P. | Exchangers | E-1405A Reboiler | Tube Bundle | VI complete | — | — | — | — | |
| 4/13/26 | Days | Dwayne P. | Exchangers | E-1401A Crude / Diesel Exchanger | Tube Bundle | VI complete | — | — | — | — | |
| 4/12/26 | Days | Dwayne P. | Exchangers | E-1404A Feed / Effluent Exchanger | Tube Bundle | VI complete | — | — | — | — | |
| 4/12/26 | Days | Dwayne P. | Exchangers | E-1408A Naphtha Cooler | Channel (Bonnet) | VI complete. Minor general corrosion, within allowance | — | — | — | — |