| Asset type | In scope | Closed out | Removed from scope | % | Discovery | Open RRs |
|---|---|---|---|---|---|---|
| Drums | 30 | 3 | 1 | 13% | 54% | 3 |
| Towers | 8 | 2 | 0 | 25% | 57% | 0 |
| Exchangers | 40 | 2 | 0 | 5% | 59% | 5 |
| Heaters | 3 | 0 | 0 | 0% | 40% | 0 |
| Fin Fans | 14 | 1 | 0 | 7% | 31% | 2 |
| PSV Pull Removed 30/50 (60%) · Installed 4/50 (8%) | 50 | 4 | 0 | 8% | — | 1 |
| Pipe & Valves | 40 | 0 |
| Asset type | Written | Closed | Deferred | Open |
|---|---|---|---|---|
| Exchangers | 9 | 1 | 3 | 5 |
| Drums | 3 | 0 | 0 | 3 |
| Fin Fans | 2 | 0 | 0 | 2 |
| Heaters | 1 | 1 | 0 | 0 |
| PSV Pull | 1 | 0 | 0 | 1 |
| Pipe & Valves | 1 | 0 | 0 | 1 |
| Total | 17 | 2 | 3 | 12 |
| RR # | Equipment / package | Asset type | Finding | Written | Status |
|---|---|---|---|---|---|
| RR-001-E-2118B | E-2118B | Exchangers | Pitting up to 0.090 in. deep in a 6 in. x 8 in. area at the 6 o'clock position of the bottom head. Remaining wall 0.410 in. against a 0.375 in. minimum. | 11/12/26 | Repair verified & closed |
| RR-002-H-2102 | H-2102 | Heaters | IRIS on 20% of tubes found 6 tubes with wall loss over 40% at the inlet end, rows 1 and 2. | 11/12/26 | Repair verified & closed |
| RR-003-E-2104A | E-2104A | Exchangers | WFMT found a 1.5 in. linear indication at the toe of the N3 nozzle-to-shell weld. | 11/13/26 | Client approved |
| RR-004-D-2194 | D-2194 | Drums | Trays 14 and 15 have two dislodged valve caps and one bent support beam. | 11/13/26 | Client approved |
| Drums · 30 in scope | ||
|---|---|---|
| D-2110 | Vertical vessel | Repair |
| D-2113 | Horizontal vessel | In progress |
| D-2116 | Horizontal vessel with boot | In progress |
| D-2119 | Vertical vessel | In progress |
| D-2122 | Vertical vessel | In progress |
| D-2125 | Horizontal vessel with boot | In progress |
| D-2128 | Horizontal vessel with boot | In progress |
| D-2131 | Vertical vessel | Closed out |
| D-2134 | Horizontal vessel with boot | In progress |
| D-2137 | Horizontal vessel with boot | In progress |
| D-2140 | Horizontal vessel with boot | In progress |
| Towers · 8 in scope | ||
|---|---|---|
| T-2101 | 36 trays | In progress |
| T-2102 | 36 trays | Closed out |
| T-2103 | 42 trays | In progress |
| T-2104 | 30 trays | In progress |
| T-2105 | 36 trays | In progress |
| T-2106 | 30 trays | In progress |
| T-2107 | 30 trays | Closed out |
| T-2108 | 42 trays | In progress |
| Exchangers · 40 in scope | ||
|---|---|---|
| E-2101A | AES shell and tube | In progress |
| E-2102A | AES shell and tube | In progress |
| E-2103B | BEU U-tube | In progress |
| E-2104A | BEU U-tube | Repair |
| E-2105A | BEU U-tube | In progress |
| E-2106B | AEL fixed tubesheet | In progress |
| E-2107A | BEU U-tube | Not started |
| E-2108A | AEL fixed tubesheet | In progress |
| E-2109B | AEL fixed tubesheet | Repair |
| E-2110A | BEU U-tube | In progress |
| E-2111A | AEL fixed tubesheet | Repair |
| E-2112B | ||
| Heaters · 3 in scope | ||
|---|---|---|
| H-2101 | Fired heater, box type | In progress |
| H-2102 | Fired heater, box type | In progress |
| H-2103 | Fired heater, box type | In progress |
| Fin Fans · 14 in scope | ||
|---|---|---|
| EA-2101 | 2 bays | In progress |
| EA-2102 | 2 bays | In progress |
| EA-2103 | 2 bays | Not started |
| EA-2104 | 4 bays | In progress |
| EA-2105 | 3 bays | Not started |
| EA-2106 | 3 bays | Closed out |
| EA-2107 | 2 bays | In progress |
| EA-2108 | 4 bays | In progress |
| EA-2109 | 4 bays | In progress |
| EA-2110 | 2 bays | In progress |
| EA-2111 | 3 bays | In progress |
| EA-2112 | 3 bays | |
| PSV Pull · 50 in scope | ||
|---|---|---|
| PSV-21300 | Overhead Accumulator | In progress |
| PSV-21302 | Fuel Gas KO | In progress |
| PSV-21304 | Steam Header | In progress |
| PSV-21306 | Exchanger Shell Side | In progress |
| PSV-21308 | Pump Discharge | In progress |
| PSV-21310 | Flash Drum | In progress |
| PSV-21312 | Reboiler Outlet | In progress |
| PSV-21314 | Tower Overhead | In progress |
| PSV-21316 | Overhead Accumulator | In progress |
| PSV-21318 | Fuel Gas KO | In progress |
| PSV-21320 | Steam Header | Closed out |
| Pipe & Valves · 40 in scope | ||
|---|---|---|
| 4"-P-2110-A1 | 304 SS | Not started |
| 8"-P-2111-B2 | 304 SS | In progress |
| 6"-P-2112-A1 | Carbon steel | Not started |
| 8"-P-2113-C1 | Carbon steel | Not started |
| 6"-P-2114-C1 | Carbon steel | In progress |
| 3"-P-2115-B2 | 304 SS | Not started |
| 8"-P-2116-C1 | Carbon steel | Not started |
| 4"-P-2117-C1 | Carbon steel | Not started |
| 12"-P-2118-B2 | 5 Cr | Not started |
| 10"-P-2119-A1 | Carbon steel | In progress |
| 6"-P-2120-C1 | 304 SS | In progress |
| Date | Shift | Inspector | Equipment | Details |
|---|---|---|---|---|
| 11/22/26 | Nights | Wes D. | PSV-21320 | PSV Installed complete. No cracking found |
| 11/22/26 | Nights | Megan F. | E-2112B | Final QA complete |
| 11/22/26 | Nights | Omar S. | E-2120A | Final QA complete |
| 11/22/26 | Nights | Wes D. | T-2107 | Final QA complete |
| 11/22/26 | Days | Priya N. | EA-2106 | Final QA complete |
| 11/22/26 | Days | Andre K. | D-2143 | Final QA complete |
| 11/22/26 | Days | Hollis B. | PSV-21336 | PSV Installed complete |
| 11/22/26 | Days |
| 0 |
| 0% |
| — |
| 1 |
| Total | 185 | 12 | 1 | 7% | 55% | 12 |
| RR-005-PSV-21378 |
| PSV-21378 |
| PSV Pull |
| Pitting across the gasket seating face of the channel flange, deepest 0.060 in. |
| 11/14/26 |
| Client approved |
| RR-006-E-2115B | E-2115B | Exchangers | About 12 sq ft of spalled castable on the north radiant wall, anchors exposed. | 11/14/26 | Client approved |
| RR-007-E-2129A | E-2129A | Exchangers | UTT at CML 7 read 0.188 in. against a 0.200 in. retirement thickness. | 11/15/26 | Client deferred |
| RR-008-E-2109B | E-2109B | Exchangers | Weeping at 3 plugs on the inlet header box, threads galled. | 11/16/26 | Lead deferred |
| RR-009-E-2112B | E-2112B | Exchangers | Pitting up to 0.090 in. deep in a 6 in. x 8 in. area at the 6 o'clock position of the bottom head. Remaining wall 0.410 in. against a 0.375 in. minimum. | 11/16/26 | Awaiting client |
| RR-010-E-2103B | E-2103B | Exchangers | IRIS on 20% of tubes found 6 tubes with wall loss over 40% at the inlet end, rows 1 and 2. | 11/17/26 | Awaiting client |
| RR-011-8"-P-2138-C1 | 8"-P-2138-C1 | Pipe & Valves | WFMT found a 1.5 in. linear indication at the toe of the N3 nozzle-to-shell weld. | 11/17/26 | Awaiting client |
| RR-012-D-2164 | D-2164 | Drums | Trays 14 and 15 have two dislodged valve caps and one bent support beam. | 11/18/26 | Awaiting supervisor review |
| RR-013-EA-2114 | EA-2114 | Fin Fans | Pitting across the gasket seating face of the channel flange, deepest 0.060 in. | 11/19/26 | Awaiting supervisor review |
| RR-014-EA-2111 | EA-2111 | Fin Fans | About 12 sq ft of spalled castable on the north radiant wall, anchors exposed. | 11/19/26 | Awaiting supervisor review |
| RR-015-E-2111A | E-2111A | Exchangers | UTT at CML 7 read 0.188 in. against a 0.200 in. retirement thickness. | 11/20/26 | Partial — write-up not finished |
| RR-016-D-2110 | D-2110 | Drums | Weeping at 3 plugs on the inlet header box, threads galled. | 11/20/26 | Client approved |
| RR-017-E-2110A | E-2110A | Exchangers | Pitting up to 0.090 in. deep in a 6 in. x 8 in. area at the 6 o'clock position of the bottom head. Remaining wall 0.410 in. against a 0.375 in. minimum. | 11/21/26 | Client deferred |
| D-2143 | Horizontal vessel | Closed out |
| D-2146 | Vertical vessel | In progress |
| D-2149 | Horizontal vessel | Closed out |
| D-2152 | Horizontal vessel with boot | In progress |
| D-2155 | Horizontal vessel | In progress |
| D-2158 | Horizontal vessel with boot | In progress |
| D-2161 | Vertical vessel | In progress |
| D-2164 | Horizontal vessel with boot | In progress |
| D-2167 | Horizontal vessel | In progress |
| D-2170 | Horizontal vessel | In progress |
| D-2173 | Vertical vessel | In progress |
| D-2176 | Vertical vessel | Removed from scope |
| D-2179 | Vertical vessel | In progress |
| D-2182 | Horizontal vessel with boot | In progress |
| D-2185 | Horizontal vessel with boot | In progress |
| D-2188 | Horizontal vessel | In progress |
| D-2191 | Vertical vessel | Not started |
| D-2194 | Horizontal vessel with boot | Repair |
| D-2197 | Vertical vessel | Not started |
| AES shell and tube |
| Closed out |
| E-2113A | AES shell and tube | Not started |
| E-2114A | AES shell and tube | In progress |
| E-2115B | BEU U-tube | Repair |
| E-2116A | AES shell and tube | In progress |
| E-2117A | AEL fixed tubesheet | Not started |
| E-2118B | BEU U-tube | In progress |
| E-2119A | AES shell and tube | In progress |
| E-2120A | AES shell and tube | Closed out |
| E-2121B | BEU U-tube | In progress |
| E-2122A | AES shell and tube | In progress |
| E-2123A | BEU U-tube | In progress |
| E-2124B | AES shell and tube | In progress |
| E-2125A | AEL fixed tubesheet | In progress |
| E-2126A | AES shell and tube | In progress |
| E-2127B | AEL fixed tubesheet | Not started |
| E-2128A | AES shell and tube | In progress |
| E-2129A | AEL fixed tubesheet | In progress |
| E-2130B | AES shell and tube | Not started |
| E-2131A | AES shell and tube | Not started |
| E-2132A | BEU U-tube | In progress |
| E-2133B | AEL fixed tubesheet | Not started |
| E-2134A | AEL fixed tubesheet | In progress |
| E-2135A | BEU U-tube | Not started |
| E-2136B | BEU U-tube | Not started |
| E-2137A | AEL fixed tubesheet | In progress |
| E-2138A | AEL fixed tubesheet | In progress |
| E-2139B | BEU U-tube | In progress |
| E-2140A | AEL fixed tubesheet | In progress |
| In progress |
| EA-2113 | 4 bays | Not started |
| EA-2114 | 4 bays | In progress |
| PSV-21322 |
| Exchanger Shell Side |
| Closed out |
| PSV-21324 | Pump Discharge | In progress |
| PSV-21326 | Flash Drum | In progress |
| PSV-21328 | Reboiler Outlet | In progress |
| PSV-21330 | Tower Overhead | In progress |
| PSV-21332 | Overhead Accumulator | In progress |
| PSV-21334 | Fuel Gas KO | In progress |
| PSV-21336 | Steam Header | Closed out |
| PSV-21338 | Exchanger Shell Side | In progress |
| PSV-21340 | Pump Discharge | Not started |
| PSV-21342 | Flash Drum | In progress |
| PSV-21344 | Reboiler Outlet | Not started |
| PSV-21346 | Tower Overhead | Not started |
| PSV-21348 | Overhead Accumulator | In progress |
| PSV-21350 | Fuel Gas KO | In progress |
| PSV-21352 | Steam Header | In progress |
| PSV-21354 | Exchanger Shell Side | Not started |
| PSV-21356 | Pump Discharge | Not started |
| PSV-21358 | Flash Drum | Closed out |
| PSV-21360 | Reboiler Outlet | In progress |
| PSV-21362 | Tower Overhead | In progress |
| PSV-21364 | Overhead Accumulator | In progress |
| PSV-21366 | Fuel Gas KO | Not started |
| PSV-21368 | Steam Header | Not started |
| PSV-21370 | Exchanger Shell Side | Not started |
| PSV-21372 | Pump Discharge | Not started |
| PSV-21374 | Flash Drum | In progress |
| PSV-21376 | Reboiler Outlet | Not started |
| PSV-21378 | Tower Overhead | Repair |
| PSV-21380 | Overhead Accumulator | In progress |
| PSV-21382 | Fuel Gas KO | In progress |
| PSV-21384 | Steam Header | In progress |
| PSV-21386 | Exchanger Shell Side | Not started |
| PSV-21388 | Pump Discharge | Not started |
| PSV-21390 | Flash Drum | In progress |
| PSV-21392 | Reboiler Outlet | In progress |
| PSV-21394 | Tower Overhead | Not started |
| PSV-21396 | Overhead Accumulator | In progress |
| PSV-21398 | Fuel Gas KO | Not started |
| 12"-P-2121-B2 |
| Carbon steel |
| Not started |
| 6"-P-2122-C1 | Carbon steel | In progress |
| 12"-P-2123-B2 | 5 Cr | Not started |
| 4"-P-2124-B2 | 304 SS | Not started |
| 6"-P-2125-A1 | 5 Cr | In progress |
| 6"-P-2126-B2 | Carbon steel | Not started |
| 12"-P-2127-C1 | 5 Cr | In progress |
| 2"-P-2128-C1 | 5 Cr | Not started |
| 8"-P-2129-B2 | Carbon steel | Not started |
| 10"-P-2130-C1 | Carbon steel | Not started |
| 12"-P-2131-C1 | 5 Cr | In progress |
| 12"-P-2132-C1 | Carbon steel | In progress |
| 3"-P-2133-A1 | Carbon steel | Not started |
| 6"-P-2134-A1 | Carbon steel | In progress |
| 3"-P-2135-C1 | Carbon steel | Not started |
| 4"-P-2136-A1 | 304 SS | Not started |
| 8"-P-2137-C1 | 304 SS | In progress |
| 8"-P-2138-C1 | 304 SS | In progress |
| 12"-P-2139-A1 | 304 SS | In progress |
| 12"-P-2140-A1 | 304 SS | Not started |
| 4"-P-2141-B2 | 304 SS | Not started |
| 4"-P-2142-B2 | 5 Cr | Not started |
| 8"-P-2143-B2 | Carbon steel | In progress |
| 2"-P-2144-B2 | Carbon steel | In progress |
| 3"-P-2145-B2 | Carbon steel | In progress |
| 10"-P-2146-A1 | 304 SS | Not started |
| 8"-P-2147-C1 | 5 Cr | In progress |
| 12"-P-2148-A1 | 5 Cr | Not started |
| 8"-P-2149-B2 | Carbon steel | Not started |
| Luis O. |
| PSV-21360 |
| Inlet Piping VT in progress |
| 11/22/26 | Days | Tasha R. | PSV-21300 | Outlet Piping VT in progress |
| 11/22/26 | Days | Dwayne P. | EA-2109 | Tube ID Gauge in progress |
| 11/22/26 | Days | Dwayne P. | PSV-21384 | Outlet Piping VT in progress |
| 11/22/26 | Days | Grant W. | E-2110A | UTT in progress |
| 11/22/26 | Days | Marcus H. | D-2122 | External Visual in progress |
| 11/22/26 | Days | Tasha R. | 8"-P-2137-C1 | External Visual in progress |
| 11/22/26 | Days | Tasha R. | D-2194 | WFMT in progress |
| 11/22/26 | Days | Luis O. | D-2140 | Flanges VI in progress |
| 11/22/26 | Days | Andre K. | E-2108A | UTT in progress |
| 11/22/26 | Days | Grant W. | PSV-21342 | Inlet Piping VT in progress |
| 11/22/26 | Days | Carla V. | E-2118B | Flanges VI in progress |
| 11/22/26 | Days | Luis O. | E-2101A | UTT in progress |
| 11/22/26 | Days | Marcus H. | PSV-21324 | PSV Installed in progress |
| 11/22/26 | Days | Luis O. | PSV-21330 | Inlet Piping VT in progress |
| 11/22/26 | Days | Andre K. | E-2128A | Final QA in progress |
| 11/22/26 | Days | Grant W. | PSV-21314 | PSV Installed in progress |
| 11/22/26 | Days | Dwayne P. | PSV-21352 | Inlet Piping VT in progress |
| 11/22/26 | Days | Marcus H. | E-2129A | UTT in progress |
| 11/22/26 | Days | Tasha R. | E-2128A | Final QA in progress |
| 11/22/26 | Days | Dwayne P. | H-2102 | Refractory in progress |
| 11/22/26 | Days | Grant W. | E-2110A | UTT in progress |
| 11/22/26 | Days | Luis O. | E-2108A | UTT in progress |
| 11/22/26 | Days | Carla V. | D-2125 | Final QA in progress |
| 11/22/26 | Days | Hollis B. | PSV-21390 | Inlet Piping VT in progress |
| 11/22/26 | Days | Dwayne P. | E-2104A | UTT in progress |
| 11/22/26 | Days | Dwayne P. | PSV-21306 | PSV Removed in progress |
| 11/22/26 | Days | Carla V. | PSV-21310 | Outlet Piping VT in progress |
| 11/22/26 | Days | Marcus H. | E-2101A | UTT in progress |
| 11/22/26 | Days | Marcus H. | E-2112B | Final QA complete |
| 11/22/26 | Days | Carla V. | T-2102 | Final QA complete |
| 11/22/26 | Days | Dwayne P. | E-2119A | ECT/RFT/IRIS in progress |
| 11/22/26 | Days | Hollis B. | E-2138A | Final QA in progress |
| 11/22/26 | Days | Grant W. | PSV-21334 | Inlet Piping VT in progress |
| 11/22/26 | Days | Luis O. | D-2170 | WFMT in progress |
| 11/22/26 | Days | Tasha R. | E-2124B | VI in progress |
| 11/22/26 | Days | Luis O. | E-2102A | Flanges VI in progress |
| 11/22/26 | Days | Hollis B. | E-2132A | UTT in progress |
| 11/22/26 | Days | Marcus H. | PSV-21378 | Outlet Piping VT in progress |
| 11/22/26 | Days | Hollis B. | E-2114A | VI in progress |
| 11/22/26 | Days | Marcus H. | D-2128 | WFMT in progress |
| 11/22/26 | Days | Marcus H. | E-2116A | UTT in progress |
| 11/22/26 | Days | Andre K. | D-2182 | UTT in progress |
| 11/22/26 | Days | Hollis B. | E-2103B | UTT in progress |
| 11/22/26 | Days | Marcus H. | D-2137 | WFMT in progress |
| 11/22/26 | Days | Tasha R. | E-2105A | VI in progress |
| 11/22/26 | Days | Carla V. | E-2138A | Final QA in progress |
| 11/22/26 | Days | Andre K. | E-2118B | Flanges VI in progress |
| 11/22/26 | Days | Hollis B. | E-2132A | UTT in progress |
| 11/22/26 | Days | Andre K. | PSV-21338 | PSV Installed in progress |
| 11/22/26 | Days | Andre K. | D-2173 | External Visual in progress |
| 11/22/26 | Days | Marcus H. | EA-2107 | VI in progress |
| 11/22/26 | Days | Grant W. | E-2134A | UTT in progress |
| 11/22/26 | Days | Carla V. | EA-2102 | Tube ID Gauge in progress |
| 11/22/26 | Days | Grant W. | PSV-21328 | Outlet Piping VT in progress |
| 11/22/26 | Days | Hollis B. | D-2164 | WFMT in progress |
| 11/22/26 | Days | Priya N. | PSV-21374 | Inlet Piping VT in progress |
| 11/22/26 | Days | Hollis B. | D-2152 | UTT in progress |
| 11/22/26 | Days | Grant W. | E-2115B | Final QA in progress |
| 11/22/26 | Days | Marcus H. | PSV-21316 | PSV Removed in progress |
| 11/22/26 | Days | Tasha R. | E-2132A | UTT in progress |
| 11/22/26 | Days | Grant W. | E-2123A | VI in progress |
| 11/22/26 | Days | Hollis B. | PSV-21350 | Outlet Piping VT in progress |
| 11/22/26 | Days | Carla V. | E-2137A | UTT in progress |
| 11/22/26 | Days | Dwayne P. | E-2120A | Final QA complete |
| 11/22/26 | Days | Hollis B. | 8"-P-2143-B2 | UTT in progress |
| 11/22/26 | Days | Priya N. | E-2124B | VI in progress |
| 11/22/26 | Days | Luis O. | E-2139B | Flanges VI in progress |
| 11/22/26 | Days | Dwayne P. | D-2188 | Internal Visual in progress |
| 11/22/26 | Days | Marcus H. | E-2109B | Flanges VI in progress |
| 11/22/26 | Days | Priya N. | 6"-P-2125-A1 | Final QA in progress |
| 11/22/26 | Days | Dwayne P. | E-2122A | ECT/RFT/IRIS in progress |
| 11/22/26 | Days | Dwayne P. | E-2109B | Flanges VI in progress |
| 11/22/26 | Days | Grant W. | E-2110A | UTT in progress |
| 11/22/26 | Days | Hollis B. | E-2129A | UTT in progress |
| 11/22/26 | Days | Luis O. | E-2104A | UTT in progress |
| 11/22/26 | Days | Grant W. | E-2102A | Flanges VI in progress |
| 11/22/26 | Days | Carla V. | E-2129A | UTT in progress |
| 11/22/26 | Days | Hollis B. | T-2106 | Flanges VI in progress |
| 11/22/26 | Days | Hollis B. | E-2104A | UTT in progress |
| 11/22/26 | Days | Priya N. | EA-2104 | VI in progress |
| 11/22/26 | Days | Luis O. | PSV-21362 | Outlet Piping VT in progress |
| 11/22/26 | Days | Carla V. | 2"-P-2144-B2 | UTT in progress |
| 11/22/26 | Days | Dwayne P. | PSV-21308 | PSV Removed in progress |
| 11/22/26 | Days | Marcus H. | E-2116A | UTT in progress |
| 11/22/26 | Days | Dwayne P. | PSV-21380 | PSV Installed in progress |
| 11/22/26 | Days | Dwayne P. | PSV-21302 | PSV Removed in progress |
| 11/22/26 | Days | Carla V. | E-2125A | ECT/RFT/IRIS in progress |
| 11/22/26 | Days | Andre K. | E-2102A | Flanges VI in progress |
| 11/22/26 | Days | Hollis B. | PSV-21364 | PSV Installed in progress |
| 11/22/26 | Nights | Wes D. | H-2103 | Radiant Section in progress |
| 11/22/26 | Nights | Megan F. | E-2111A | ECT/RFT/IRIS in progress |
| 11/22/26 | Nights | Kendra J. | E-2139B | Flanges VI in progress |
| 11/22/26 | Nights | Wes D. | 8"-P-2147-C1 | External Visual in progress |
| 11/22/26 | Nights | Omar S. | PSV-21392 | Outlet Piping VT in progress |
| 11/22/26 | Nights | Wes D. | E-2108A | UTT in progress |
| 11/22/26 | Nights | Wes D. | D-2155 | Flanges VI in progress |
| 11/22/26 | Nights | Omar S. | D-2134 | Flanges VI in progress |
| 11/22/26 | Nights | Megan F. | PSV-21318 | Inlet Piping VT in progress |
| 11/22/26 | Nights | Rusty C. | EA-2110 | VI in progress |
| 11/22/26 | Nights | Kendra J. | E-2105A | VI in progress |
| 11/22/26 | Nights | Megan F. | E-2116A | UTT in progress |
| 11/22/26 | Nights | Wes D. | E-2115B | Final QA in progress |
| 11/22/26 | Nights | Megan F. | E-2126A | ECT/RFT/IRIS in progress |
| 11/22/26 | Nights | Kendra J. | E-2104A | UTT in progress |
| 11/22/26 | Nights | Kendra J. | 12"-P-2139-A1 | External Visual in progress |
| 11/22/26 | Nights | Kendra J. | D-2116 | UTT in progress |
| 11/22/26 | Nights | Omar S. | E-2123A | VI in progress |
| 11/22/26 | Nights | Kendra J. | E-2115B | Final QA in progress |
| 11/22/26 | Nights | Rusty C. | E-2138A | Final QA in progress |
| 11/22/26 | Nights | Wes D. | PSV-21396 | Outlet Piping VT in progress |
| 11/22/26 | Nights | Rusty C. | E-2140A | ECT/RFT/IRIS in progress |
| 11/22/26 | Nights | Omar S. | E-2137A | UTT in progress |
| 11/22/26 | Nights | Wes D. | PSV-21312 | PSV Installed in progress |
| 11/22/26 | Nights | Omar S. | E-2114A | VI in progress |
| 11/22/26 | Nights | Megan F. | E-2129A | UTT in progress |
| 11/22/26 | Nights | Omar S. | EA-2111 | Final QA in progress |
| 11/22/26 | Nights | Megan F. | E-2106B | Flanges VI in progress |
| 11/22/26 | Nights | Megan F. | E-2103B | UTT in progress |
| 11/22/26 | Nights | Megan F. | E-2121B | UTT in progress |
| 11/22/26 | Nights | Rusty C. | E-2105A | VI in progress |
| 11/22/26 | Nights | Megan F. | E-2109B | Flanges VI in progress |
| 11/22/26 | Nights | Rusty C. | PSV-21304 | Outlet Piping VT in progress |
| 11/22/26 | Nights | Rusty C. | H-2101 | Convection in progress |
| 11/22/26 | Nights | Omar S. | T-2101 | Internal Visual in progress |
| 11/22/26 | Nights | Megan F. | E-2121B | UTT in progress |
| 11/22/26 | Nights | Omar S. | E-2123A | VI in progress |
| 11/22/26 | Nights | Omar S. | T-2103 | PAUT/UTSW in progress |
| 11/22/26 | Nights | Megan F. | E-2121B | UTT in progress |
| 11/22/26 | Nights | Megan F. | E-2128A | Final QA in progress |
| 11/22/26 | Nights | Wes D. | E-2134A | UTT in progress |
| 11/22/26 | Nights | Megan F. | EA-2112 | Final QA in progress |
| 11/22/26 | Nights | Omar S. | E-2109B | Flanges VI in progress |
| 11/22/26 | Nights | Wes D. | E-2124B | VI in progress |
| 11/21/26 | Nights | Megan F. | E-2120A | Final QA complete |
| 11/21/26 | Nights | Kendra J. | E-2112B | Final QA complete |
| 11/21/26 | Nights | Wes D. | PSV-21322 | PSV Installed complete |
| 11/21/26 | Days | Dwayne P. | D-2149 | Final QA complete |
| 11/21/26 | Days | Tasha R. | E-2120A | Final QA complete |
| 11/21/26 | Days | Grant W. | E-2112B | Final QA complete |
| 11/21/26 | Days | Marcus H. | D-2131 | Final QA complete |
| 11/20/26 | Nights | Kendra J. | PSV-21358 | PSV Installed complete. Gaskets surfaces good |
| 11/20/26 | Nights | Rusty C. | E-2128A | UTT complete |
| 11/20/26 | Nights | Megan F. | E-2115B | UTT complete. Coating intact |
| 11/20/26 | Nights | Rusty C. | D-2158 | Flanges VI complete |
| 11/20/26 | Days | Andre K. | E-2120A | UTT complete |
| 11/20/26 | Days | Priya N. | E-2120A | UTT complete |
| 11/20/26 | Days | Andre K. | E-2120A | UTT complete. No cracking found |
| 11/20/26 | Days | Tasha R. | T-2107 | Flanges VI complete |
| 11/20/26 | Days | Marcus H. | D-2149 | Flanges VI complete |
| 11/19/26 | Nights | Rusty C. | D-2125 | Flanges VI complete. No cracking found |
| 11/19/26 | Nights | Rusty C. | EA-2111 | Flanges VI complete. No cracking found |
| 11/19/26 | Nights | Omar S. | T-2102 | Flanges VI complete. No cracking found |
| 11/19/26 | Nights | Megan F. | PSV-21358 | Outlet Piping VT complete. Minor general corrosion, within allowance |
| 11/19/26 | Days | Dwayne P. | D-2143 | Flanges VI complete |
| 11/19/26 | Days | Dwayne P. | D-2167 | Flanges VI complete. Coating intact |
| 11/19/26 | Days | Grant W. | E-2112B | UTT complete |
| 11/19/26 | Days | Priya N. | PSV-21320 | Outlet Piping VT complete. No cracking found |
| 11/19/26 | Days | Dwayne P. | E-2128A | UTT complete |
| 11/19/26 | Days | Carla V. | E-2138A | UTT complete |
| 11/19/26 | Days | Dwayne P. | D-2131 | Flanges VI complete |
| 11/19/26 | Days | Andre K. | E-2120A | UTT complete. No cracking found |
| 11/19/26 | Days | Luis O. | PSV-21336 | Outlet Piping VT complete. Light scale, no pitting |
| 11/19/26 | Days | Hollis B. | E-2115B | UTT complete. No cracking found |
| 11/19/26 | Days | Grant W. | E-2128A | UTT complete |
| 11/19/26 | Days | Tasha R. | PSV-21312 | Outlet Piping VT complete |
| 11/18/26 | Nights | Rusty C. | E-2112B | UTT complete |
| 11/18/26 | Nights | Kendra J. | PSV-21314 | Outlet Piping VT complete. No recordable indications |
| 11/18/26 | Nights | Wes D. | E-2115B | UTT complete |
| 11/18/26 | Nights | Wes D. | E-2112B | UTT complete |
| 11/18/26 | Nights | Omar S. | D-2131 | WFMT complete. Coating intact |
| 11/18/26 | Nights | Wes D. | E-2115B | UTT complete. Gaskets surfaces good |
| 11/18/26 | Nights | Omar S. | E-2128A | UTT complete |
| 11/18/26 | Days | Marcus H. | E-2138A | UTT complete. Minor general corrosion, within allowance |
| 11/18/26 | Days | Hollis B. | PSV-21364 | Outlet Piping VT complete |
| 11/18/26 | Days | Tasha R. | E-2138A | UTT complete |
| 11/18/26 | Days | Luis O. | D-2125 | WFMT complete |
| 11/18/26 | Days | Dwayne P. | E-2112B | UTT complete. No cracking found |
| 11/18/26 | Days | Luis O. | E-2138A | UTT complete |
| 11/17/26 | Nights | Omar S. | T-2107 | PAUT/UTSW complete. Minor general corrosion, within allowance |
| 11/17/26 | Nights | Wes D. | D-2149 | WFMT complete |
| 11/17/26 | Nights | Megan F. | D-2155 | WFMT complete. No recordable indications |
| 11/17/26 | Nights | Megan F. | 6"-P-2125-A1 | UTT complete. Light scale, no pitting |
| 11/17/26 | Days | Grant W. | D-2158 | WFMT complete |
| 11/17/26 | Days | Dwayne P. | T-2102 | PAUT/UTSW complete. Minor general corrosion, within allowance |
| 11/17/26 | Days | Priya N. | PSV-21322 | Outlet Piping VT complete |
| 11/17/26 | Days | Carla V. | D-2167 | WFMT complete. Coating intact |
| 11/17/26 | Days | Carla V. | PSV-21382 | Outlet Piping VT complete. Light scale, no pitting |
| 11/17/26 | Days | Luis O. | T-2106 | PAUT/UTSW complete. No recordable indications |
| 11/17/26 | Days | Carla V. | E-2116A | ECT/RFT/IRIS complete. Light scale, no pitting |
| 11/17/26 | Days | Luis O. | E-2115B | ECT/RFT/IRIS complete. Light scale, no pitting |
| 11/17/26 | Days | Hollis B. | PSV-21338 | Outlet Piping VT complete |
| 11/17/26 | Days | Tasha R. | E-2138A | ECT/RFT/IRIS complete |
| 11/17/26 | Days | Marcus H. | E-2112B | ECT/RFT/IRIS complete |
| 11/17/26 | Days | Dwayne P. | EA-2106 | Flanges VI complete. No recordable indications |
| 11/17/26 | Days | Carla V. | PSV-21380 | Outlet Piping VT complete |
| 11/17/26 | Days | Hollis B. | D-2143 | WFMT complete. Light scale, no pitting |
| 11/16/26 | Nights | Wes D. | D-2134 | WFMT complete |
| 11/16/26 | Nights | Wes D. | D-2155 | UTT complete |
| 11/16/26 | Nights | Wes D. | E-2121B | ECT/RFT/IRIS complete. Light scale, no pitting |
| 11/16/26 | Nights | Rusty C. | PSV-21324 | Outlet Piping VT complete |
| 11/16/26 | Nights | Rusty C. | E-2137A | ECT/RFT/IRIS complete |
| 11/16/26 | Nights | Kendra J. | PSV-21364 | Inlet Piping VT complete. No cracking found |
| 11/16/26 | Nights | Rusty C. | E-2120A | ECT/RFT/IRIS complete |
| 11/16/26 | Nights | Megan F. | T-2102 | UTT complete |
| 11/16/26 | Nights | Wes D. | E-2110A | ECT/RFT/IRIS complete. Minor general corrosion, within allowance |
| 11/16/26 | Nights | Kendra J. | PSV-21320 | Inlet Piping VT complete |
| 11/16/26 | Days | Dwayne P. | E-2132A | ECT/RFT/IRIS complete |
| 11/16/26 | Days | Tasha R. | E-2128A | ECT/RFT/IRIS complete |
| 11/16/26 | Days | Hollis B. | D-2140 | WFMT complete |
| 11/16/26 | Days | Hollis B. | E-2129A | ECT/RFT/IRIS complete |
| 11/16/26 | Days | Andre K. | E-2134A | ECT/RFT/IRIS complete |
| 11/16/26 | Days | Priya N. | T-2107 | UTT complete. Gaskets surfaces good |
| 11/16/26 | Days | Marcus H. | E-2108A | ECT/RFT/IRIS complete |
| 11/16/26 | Days | Carla V. | PSV-21380 | Inlet Piping VT complete |
| 11/16/26 | Days | Tasha R. | EA-2112 | Flanges VI complete |
| 11/16/26 | Days | Luis O. | PSV-21322 | Inlet Piping VT complete. Light scale, no pitting |
| 11/16/26 | Days | Andre K. | E-2104A | ECT/RFT/IRIS complete. Light scale, no pitting |
| 11/15/26 | Nights | Omar S. | D-2110 | UTT complete |
| 11/15/26 | Nights | Rusty C. | D-2131 | UTT complete |
| 11/15/26 | Nights | Wes D. | E-2121B | Flanges VI complete |
| 11/15/26 | Nights | Wes D. | D-2149 | UTT complete |
| 11/15/26 | Nights | Kendra J. | PSV-21382 | Inlet Piping VT complete |
| 11/15/26 | Nights | Megan F. | D-2167 | UTT complete. No recordable indications |
| 11/15/26 | Nights | Rusty C. | 10"-P-2119-A1 | UTT complete |
| 11/15/26 | Nights | Wes D. | D-2143 | UTT complete |
| 11/15/26 | Nights | Megan F. | T-2106 | UTT complete |
| 11/15/26 | Days | Grant W. | E-2116A | Flanges VI complete |
| 11/15/26 | Days | Dwayne P. | E-2115B | Flanges VI complete |
| 11/15/26 | Days | Dwayne P. | PSV-21336 | Inlet Piping VT complete. No recordable indications |
| 11/15/26 | Days | Andre K. | EA-2106 | Tube ID Gauge complete. Gaskets surfaces good |
| 11/15/26 | Days | Carla V. | H-2102 | Convection complete. No cracking found |
| 11/15/26 | Days | Dwayne P. | E-2138A | Flanges VI complete |
| 11/15/26 | Days | Marcus H. | PSV-21312 | Inlet Piping VT complete |
| 11/15/26 | Days | Grant W. | PSV-21378 | Inlet Piping VT complete |
| 11/15/26 | Days | Andre K. | EA-2111 | Tube ID Gauge complete |
| 11/15/26 | Days | Hollis B. | PSV-21362 | Inlet Piping VT complete |
| 11/15/26 | Days | Dwayne P. | E-2103B | ECT/RFT/IRIS complete |
| 11/15/26 | Days | Tasha R. | E-2120A | Flanges VI complete |
| 11/15/26 | Days | Dwayne P. | D-2158 | UTT complete. No recordable indications |
| 11/15/26 | Days | Marcus H. | E-2137A | Flanges VI complete |
| 11/15/26 | Days | Dwayne P. | D-2125 | UTT complete |
| 11/15/26 | Days | Dwayne P. | E-2128A | Flanges VI complete. Minor general corrosion, within allowance |
| 11/15/26 | Days | Grant W. | E-2115B | Flanges VI complete. Gaskets surfaces good |
| 11/15/26 | Days | Carla V. | EA-2112 | Tube ID Gauge complete. Coating intact |
| 11/15/26 | Days | Priya N. | D-2140 | UTT complete |
| 11/14/26 | Nights | Omar S. | E-2111A | Flanges VI complete |
| 11/14/26 | Nights | Kendra J. | PSV-21314 | Inlet Piping VT complete. Gaskets surfaces good |
| 11/14/26 | Nights | Rusty C. | T-2104 | External Visual complete |
| 11/14/26 | Nights | Wes D. | E-2138A | Flanges VI complete |
| 11/14/26 | Nights | Megan F. | E-2110A | Flanges VI complete. Light scale, no pitting |
| 11/14/26 | Nights | Wes D. | T-2107 | External Visual complete. Gaskets surfaces good |
| 11/14/26 | Nights | Wes D. | E-2101A | Flanges VI complete |
| 11/14/26 | Nights | Wes D. | E-2121B | Flanges VI complete |
| 11/14/26 | Nights | Megan F. | E-2116A | Flanges VI complete |
| 11/14/26 | Nights | Rusty C. | D-2167 | External Visual complete. Minor general corrosion, within allowance |
| 11/14/26 | Nights | Omar S. | E-2120A | Flanges VI complete. Light scale, no pitting |
| 11/14/26 | Nights | Omar S. | E-2137A | Flanges VI complete. Gaskets surfaces good |
| 11/14/26 | Nights | Rusty C. | D-2113 | UTT complete. No recordable indications |
| 11/14/26 | Nights | Wes D. | E-2110A | Flanges VI complete. Minor general corrosion, within allowance |
| 11/14/26 | Nights | Wes D. | T-2103 | UTT complete. Light scale, no pitting |
| 11/14/26 | Nights | Rusty C. | PSV-21348 | Inlet Piping VT complete |
| 11/14/26 | Nights | Wes D. | E-2120A | Flanges VI complete. No recordable indications |
| 11/14/26 | Nights | Rusty C. | PSV-21324 | Inlet Piping VT complete |
| 11/14/26 | Nights | Omar S. | D-2158 | External Visual complete |
| 11/14/26 | Nights | Rusty C. | PSV-21338 | Inlet Piping VT complete. No cracking found |
| 11/14/26 | Nights | Rusty C. | T-2105 | UTT complete. No cracking found |
| 11/14/26 | Nights | Rusty C. | E-2111A | Flanges VI complete. Light scale, no pitting |
| 11/14/26 | Nights | Omar S. | E-2120A | Flanges VI complete. Minor general corrosion, within allowance |
| 11/14/26 | Nights | Omar S. | E-2129A | Flanges VI complete |
| 11/14/26 | Nights | Kendra J. | E-2111A | Flanges VI complete. No recordable indications |
| 11/14/26 | Nights | Omar S. | E-2116A | Flanges VI complete |
| 11/14/26 | Nights | Rusty C. | D-2140 | External Visual complete |
| 11/14/26 | Nights | Kendra J. | D-2179 | UTT complete |
| 11/14/26 | Nights | Kendra J. | E-2116A | Flanges VI complete |
| 11/14/26 | Nights | Wes D. | E-2103B | Flanges VI complete. No cracking found |
| 11/14/26 | Days | Grant W. | E-2112B | Flanges VI complete. Light scale, no pitting |
| 11/14/26 | Days | Priya N. | E-2121B | Flanges VI complete. Gaskets surfaces good |
| 11/14/26 | Days | Dwayne P. | E-2119A | Flanges VI complete |
| 11/14/26 | Days | Carla V. | D-2137 | UTT complete. No cracking found |
| 11/14/26 | Days | Marcus H. | E-2110A | Flanges VI complete |
| 11/14/26 | Days | Carla V. | E-2134A | Flanges VI complete |
| 11/14/26 | Days | Grant W. | E-2108A | Flanges VI complete. No cracking found |
| 11/14/26 | Days | Andre K. | PSV-21304 | Inlet Piping VT complete |
| 11/14/26 | Days | Dwayne P. | E-2119A | Flanges VI complete |
| 11/14/26 | Days | Grant W. | E-2112B | Flanges VI complete |
| 11/14/26 | Days | Hollis B. | E-2101A | Flanges VI complete |
| 11/14/26 | Days | Dwayne P. | D-2194 | UTT complete |
| 11/14/26 | Days | Luis O. | E-2104A | Flanges VI complete |
| 11/14/26 | Days | Andre K. | E-2128A | Flanges VI complete. No cracking found |
| 11/14/26 | Days | Luis O. | PSV-21350 | Inlet Piping VT complete |
| 11/14/26 | Days | Hollis B. | E-2101A | Flanges VI complete |
| 11/14/26 | Days | Priya N. | D-2131 | External Visual complete |
| 11/14/26 | Days | Carla V. | D-2164 | UTT complete |
| 11/14/26 | Days | Priya N. | T-2104 | UTT complete |
| 11/14/26 | Days | Andre K. | E-2122A | Flanges VI complete |
| 11/14/26 | Days | Hollis B. | PSV-21328 | Inlet Piping VT complete. Gaskets surfaces good |
| 11/14/26 | Days | Marcus H. | E-2112B | Flanges VI complete |
| 11/14/26 | Days | Tasha R. | E-2128A | Flanges VI complete |
| 11/14/26 | Days | Tasha R. | 6"-P-2125-A1 | External Visual complete |
| 11/14/26 | Days | Hollis B. | E-2101A | Flanges VI complete |
| 11/14/26 | Days | Priya N. | E-2132A | Flanges VI complete. No cracking found |
| 11/14/26 | Days | Hollis B. | E-2129A | Flanges VI complete. Gaskets surfaces good |
| 11/14/26 | Days | Andre K. | E-2111A | Flanges VI complete |
| 11/14/26 | Days | Tasha R. | E-2103B | Flanges VI complete |
| 11/14/26 | Days | Grant W. | PSV-21396 | Inlet Piping VT complete. Minor general corrosion, within allowance |
| 11/14/26 | Days | Dwayne P. | E-2115B | Flanges VI complete |
| 11/14/26 | Days | Marcus H. | D-2134 | UTT complete |
| 11/14/26 | Days | Andre K. | E-2134A | Flanges VI complete |
| 11/14/26 | Days | Hollis B. | E-2122A | Flanges VI complete |
| 11/14/26 | Days | Andre K. | E-2108A | Flanges VI complete. Gaskets surfaces good |
| 11/14/26 | Days | Grant W. | PSV-21358 | Inlet Piping VT complete. Light scale, no pitting |
| 11/14/26 | Days | Dwayne P. | E-2112B | Flanges VI complete. Light scale, no pitting |
| 11/14/26 | Days | Luis O. | E-2108A | Flanges VI complete |
| 11/14/26 | Days | Hollis B. | E-2101A | ECT/RFT/IRIS complete |
| 11/13/26 | Nights | Rusty C. | D-2119 | External Visual complete |
| 11/13/26 | Nights | Megan F. | E-2129A | Flanges VI complete |
| 11/13/26 | Nights | Omar S. | E-2138A | Flanges VI complete |
| 11/13/26 | Nights | Megan F. | D-2137 | External Visual complete. Coating intact |
| 11/13/26 | Nights | Wes D. | D-2113 | External Visual complete |
| 11/13/26 | Nights | Kendra J. | PSV-21300 | Inlet Piping VT complete |
| 11/13/26 | Nights | Wes D. | PSV-21358 | PSV Removed complete |
| 11/13/26 | Nights | Megan F. | D-2149 | External Visual complete |
| 11/13/26 | Nights | Rusty C. | E-2104A | Flanges VI complete |
| 11/13/26 | Nights | Megan F. | E-2115B | Flanges VI complete |
| 11/13/26 | Nights | Omar S. | E-2138A | VI complete |
| 11/13/26 | Nights | Rusty C. | D-2164 | External Visual complete. Minor general corrosion, within allowance |
| 11/13/26 | Nights | Megan F. | PSV-21310 | PSV Removed complete. Light scale, no pitting |
| 11/13/26 | Nights | Omar S. | D-2170 | External Visual complete |
| 11/13/26 | Nights | Omar S. | D-2110 | External Visual complete. Minor general corrosion, within allowance |
| 11/13/26 | Nights | Omar S. | E-2110A | Flanges VI complete. No recordable indications |
| 11/13/26 | Nights | Omar S. | E-2121B | Flanges VI complete. Gaskets surfaces good |
| 11/13/26 | Nights | Kendra J. | D-2143 | External Visual complete |
| 11/13/26 | Nights | Rusty C. | E-2132A | Flanges VI complete |
| 11/13/26 | Nights | Omar S. | E-2132A | Flanges VI complete |
| 11/13/26 | Days | Carla V. | E-2125A | Flanges VI complete |
| 11/13/26 | Days | Luis O. | E-2103B | Flanges VI complete |
| 11/13/26 | Days | Carla V. | E-2134A | Flanges VI complete. Minor general corrosion, within allowance |
| 11/13/26 | Days | Grant W. | E-2134A | VI complete. Coating intact |
| 11/13/26 | Days | Marcus H. | D-2194 | External Visual complete. Coating intact |
| 11/13/26 | Days | Hollis B. | E-2126A | Flanges VI complete |
| 11/13/26 | Days | Hollis B. | E-2125A | Flanges VI complete |
| 11/13/26 | Days | Dwayne P. | E-2140A | Flanges VI complete |
| 11/13/26 | Days | Marcus H. | E-2125A | Flanges VI complete. Coating intact |
| 11/13/26 | Days | Grant W. | E-2122A | Flanges VI complete |
| 11/13/26 | Days | Carla V. | E-2128A | Flanges VI complete |
| 11/13/26 | Days | Tasha R. | E-2138A | Flanges VI complete. Light scale, no pitting |
| 11/13/26 | Days | Hollis B. | E-2104A | Flanges VI complete |
| 11/13/26 | Days | Priya N. | D-2134 | External Visual complete |
| 11/13/26 | Days | Carla V. | E-2140A | Flanges VI complete |
| 11/13/26 | Days | Luis O. | E-2104A | Flanges VI complete |
| 11/13/26 | Days | Tasha R. | PSV-21310 | Inlet Piping VT complete. Light scale, no pitting |
| 11/13/26 | Days | Grant W. | E-2129A | VI complete |
| 11/13/26 | Days | Tasha R. | E-2137A | Flanges VI complete. Gaskets surfaces good |
| 11/13/26 | Days | Tasha R. | E-2108A | Flanges VI complete |
| 11/13/26 | Days | Luis O. | PSV-21392 | Inlet Piping VT complete |
| 11/13/26 | Days | Grant W. | D-2155 | External Visual complete |
| 11/13/26 | Days | Hollis B. | EA-2111 | VI complete |
| 11/13/26 | Days | Dwayne P. | H-2102 | Radiant Section complete. Gaskets surfaces good |
| 11/13/26 | Days | Marcus H. | E-2125A | Flanges VI complete |
| 11/13/26 | Days | Grant W. | PSV-21384 | Inlet Piping VT complete |
| 11/13/26 | Days | Priya N. | E-2138A | VI complete. Light scale, no pitting |
| 11/13/26 | Days | Andre K. | E-2140A | Flanges VI complete. Gaskets surfaces good |
| 11/13/26 | Days | Luis O. | PSV-21380 | PSV Removed complete. Coating intact |
| 11/13/26 | Days | Carla V. | D-2125 | External Visual complete. Coating intact |
| 11/13/26 | Days | Tasha R. | T-2106 | External Visual complete |
| 11/13/26 | Days | Luis O. | H-2101 | Radiant Section complete. No cracking found |
| 11/13/26 | Days | Hollis B. | E-2129A | Flanges VI complete |
| 11/13/26 | Days | Andre K. | D-2179 | External Visual complete |
| 11/13/26 | Days | Priya N. | D-2128 | UTT complete |
| 11/13/26 | Days | Tasha R. | 8"-P-2143-B2 | External Visual complete |
| 11/13/26 | Days | Hollis B. | E-2119A | Flanges VI complete |
| 11/13/26 | Days | Dwayne P. | E-2134A | Flanges VI complete |
| 11/13/26 | Days | Andre K. | E-2137A | Flanges VI complete. Coating intact |
| 11/13/26 | Days | Luis O. | E-2103B | Flanges VI complete |
| 11/13/26 | Days | Hollis B. | E-2126A | Flanges VI complete. No cracking found |
| 11/13/26 | Days | Carla V. | E-2122A | Flanges VI complete |
| 11/13/26 | Days | Hollis B. | 8"-P-2138-C1 | External Visual complete. Gaskets surfaces good |
| 11/13/26 | Days | Luis O. | D-2170 | UTT complete. No cracking found |
| 11/13/26 | Days | Dwayne P. | E-2126A | Flanges VI complete. Gaskets surfaces good |
| 11/13/26 | Days | Marcus H. | PSV-21378 | PSV Removed complete. Minor general corrosion, within allowance |
| 11/13/26 | Days | Dwayne P. | E-2138A | VI complete |
| 11/13/26 | Days | Andre K. | E-2119A | Flanges VI complete. No cracking found |
| 11/13/26 | Days | Hollis B. | E-2132A | Flanges VI complete |
| 11/13/26 | Days | Priya N. | T-2102 | External Visual complete |
| 11/12/26 | Nights | Rusty C. | D-2158 | Internal Visual complete. No recordable indications |
| 11/12/26 | Nights | Megan F. | E-2125A | VI complete. Coating intact |
| 11/12/26 | Nights | Omar S. | E-2109B | VI complete |
| 11/12/26 | Nights | Megan F. | E-2128A | VI complete |
| 11/12/26 | Nights | Omar S. | E-2122A | VI complete |
| 11/12/26 | Nights | Wes D. | PSV-21360 | PSV Removed complete |
| 11/12/26 | Nights | Megan F. | E-2128A | VI complete. No cracking found |
| 11/12/26 | Nights | Omar S. | E-2116A | VI complete |
| 11/12/26 | Nights | Rusty C. | E-2126A | VI complete |
| 11/12/26 | Nights | Megan F. | E-2139B | VI complete. Minor general corrosion, within allowance |
| 11/12/26 | Nights | Wes D. | E-2112B | VI complete. No cracking found |
| 11/12/26 | Nights | Kendra J. | E-2126A | Flanges VI complete. Light scale, no pitting |
| 11/12/26 | Nights | Megan F. | E-2120A | VI complete. Minor general corrosion, within allowance |
| 11/12/26 | Nights | Rusty C. | EA-2112 | VI complete |
| 11/12/26 | Nights | Kendra J. | E-2128A | VI complete. Minor general corrosion, within allowance |
| 11/12/26 | Nights | Megan F. | PSV-21392 | PSV Removed complete. No recordable indications |
| 11/12/26 | Nights | Wes D. | PSV-21348 | PSV Removed complete |
| 11/12/26 | Nights | Megan F. | H-2102 | Burners complete. Gaskets surfaces good |
| 11/12/26 | Nights | Rusty C. | D-2170 | Internal Visual complete |
| 11/12/26 | Nights | Rusty C. | E-2109B | VI complete |
| 11/12/26 | Nights | Megan F. | E-2132A | VI complete. No recordable indications |
| 11/12/26 | Nights | Kendra J. | E-2119A | VI complete |
| 11/12/26 | Nights | Omar S. | EA-2109 | VI complete |
| 11/12/26 | Nights | Wes D. | E-2101A | VI complete |
| 11/12/26 | Nights | Rusty C. | E-2112B | VI complete. Gaskets surfaces good |
| 11/12/26 | Nights | Rusty C. | E-2119A | VI complete |
| 11/12/26 | Nights | Kendra J. | D-2161 | External Visual complete |
| 11/12/26 | Nights | Kendra J. | E-2139B | VI complete. Minor general corrosion, within allowance |
| 11/12/26 | Days | Dwayne P. | T-2104 | Internal Visual complete |
| 11/12/26 | Days | Priya N. | PSV-21314 | PSV Removed complete |
| 11/12/26 | Days | Priya N. | EA-2102 | VI complete |
| 11/12/26 | Days | Andre K. | D-2137 | Internal Visual complete |
| 11/12/26 | Days | Dwayne P. | PSV-21304 | PSV Removed complete. No cracking found |
| 11/12/26 | Days | Carla V. | T-2103 | External Visual complete |
| 11/12/26 | Days | Dwayne P. | E-2140A | VI complete. Gaskets surfaces good |
| 11/12/26 | Days | Priya N. | T-2105 | External Visual complete. Light scale, no pitting |
| 11/12/26 | Days | Marcus H. | E-2140A | VI complete |
| 11/12/26 | Days | Tasha R. | E-2137A | VI complete |
| 11/12/26 | Days | Hollis B. | E-2140A | Flanges VI complete. Light scale, no pitting |
| 11/12/26 | Days | Luis O. | EA-2114 | VI complete |
| 11/12/26 | Days | Andre K. | 6"-P-2114-C1 | External Visual complete |
| 11/12/26 | Days | Andre K. | E-2104A | VI complete |
| 11/12/26 | Days | Dwayne P. | E-2132A | VI complete |
| 11/12/26 | Days | Marcus H. | D-2155 | Internal Visual complete |
| 11/12/26 | Days | Marcus H. | E-2110A | VI complete. Coating intact |
| 11/12/26 | Days | Tasha R. | D-2110 | Internal Visual complete |
| 11/12/26 | Days | Hollis B. | D-2134 | Internal Visual complete |
| 11/12/26 | Days | Luis O. | E-2108A | VI complete. Minor general corrosion, within allowance |
| 11/12/26 | Days | Hollis B. | 10"-P-2119-A1 | External Visual complete |
| 11/12/26 | Days | Dwayne P. | E-2121B | VI complete. Gaskets surfaces good |
| 11/12/26 | Days | Dwayne P. | T-2105 | Internal Visual complete |
| 11/12/26 | Days | Priya N. | E-2137A | VI complete |
| 11/12/26 | Days | Marcus H. | E-2129A | VI complete. No cracking found |
| 11/12/26 | Days | Dwayne P. | E-2103B | VI complete. No recordable indications |
| 11/12/26 | Days | Andre K. | E-2129A | VI complete. No recordable indications |
| 11/12/26 | Days | Hollis B. | PSV-21384 | PSV Removed complete. Minor general corrosion, within allowance |
| 11/12/26 | Days | Tasha R. | D-2116 | External Visual complete. Gaskets surfaces good |
| 11/12/26 | Days | Tasha R. | D-2185 | External Visual complete |
| 11/12/26 | Days | Grant W. | PSV-21324 | PSV Removed complete. Minor general corrosion, within allowance |
| 11/12/26 | Days | Hollis B. | E-2120A | VI complete |
| 11/12/26 | Days | Priya N. | E-2104A | VI complete |
| 11/12/26 | Days | Luis O. | PSV-21374 | PSV Removed complete. No cracking found |
| 11/12/26 | Days | Dwayne P. | PSV-21320 | PSV Removed complete. No recordable indications |
| 11/12/26 | Days | Hollis B. | D-2125 | Internal Visual complete. Light scale, no pitting |
| 11/12/26 | Days | Andre K. | E-2101A | VI complete |
| 11/12/26 | Days | Marcus H. | E-2103B | VI complete. No cracking found |
| 11/12/26 | Days | Carla V. | E-2110A | VI complete |
| 11/12/26 | Days | Dwayne P. | D-2152 | External Visual complete |
| 11/12/26 | Days | Carla V. | E-2104A | VI complete |
| 11/12/26 | Days | Hollis B. | E-2122A | VI complete. Coating intact |
| 11/12/26 | Days | Grant W. | PSV-21396 | PSV Removed complete |
| 11/12/26 | Days | Tasha R. | E-2110A | VI complete. No cracking found |
| 11/12/26 | Days | Carla V. | E-2126A | VI complete. No cracking found |
| 11/12/26 | Days | Dwayne P. | E-2125A | VI complete |
| 11/12/26 | Days | Grant W. | D-2128 | External Visual complete. No recordable indications |
| 11/12/26 | Days | Hollis B. | PSV-21318 | PSV Removed complete. No recordable indications |
| 11/12/26 | Days | Dwayne P. | D-2182 | External Visual complete. Minor general corrosion, within allowance |
| 11/12/26 | Days | Marcus H. | E-2116A | VI complete |
| 11/11/26 | Nights | Wes D. | E-2109B | VI complete. No cracking found |
| 11/11/26 | Nights | Omar S. | PSV-21390 | PSV Removed complete |
| 11/11/26 | Nights | Megan F. | PSV-21350 | PSV Removed complete. Minor general corrosion, within allowance |
| 11/11/26 | Nights | Omar S. | E-2126A | VI complete. No cracking found |
| 11/11/26 | Nights | Megan F. | E-2139B | VI complete. No cracking found |
| 11/11/26 | Nights | Kendra J. | 2"-P-2144-B2 | External Visual complete. Light scale, no pitting |
| 11/11/26 | Nights | Rusty C. | T-2106 | Internal Visual complete |
| 11/11/26 | Nights | Rusty C. | PSV-21352 | PSV Removed complete |
| 11/11/26 | Nights | Kendra J. | E-2118B | VI complete |
| 11/11/26 | Nights | Megan F. | E-2128A | VI complete |
| 11/11/26 | Nights | Megan F. | E-2112B | VI complete |
| 11/11/26 | Nights | Kendra J. | E-2102A | VI complete |
| 11/11/26 | Nights | Kendra J. | D-2179 | Internal Visual complete |
| 11/11/26 | Nights | Kendra J. | D-2167 | Internal Visual complete |
| 11/11/26 | Nights | Megan F. | E-2111A | VI complete. Gaskets surfaces good |
| 11/11/26 | Nights | Kendra J. | E-2118B | VI complete. Gaskets surfaces good |
| 11/11/26 | Nights | Omar S. | E-2132A | VI complete |
| 11/11/26 | Nights | Kendra J. | E-2125A | VI complete |
| 11/11/26 | Nights | Wes D. | E-2122A | VI complete. Minor general corrosion, within allowance |
| 11/11/26 | Nights | Wes D. | T-2107 | Internal Visual complete |
| 11/11/26 | Nights | Megan F. | E-2137A | VI complete. No cracking found |
| 11/11/26 | Nights | Rusty C. | D-2152 | Internal Visual complete |
| 11/11/26 | Nights | Wes D. | D-2128 | Internal Visual complete |
| 11/11/26 | Nights | Megan F. | D-2161 | Internal Visual complete. Gaskets surfaces good |
| 11/11/26 | Nights | Omar S. | E-2139B | VI complete |
| 11/11/26 | Nights | Kendra J. | E-2119A | VI complete |
| 11/11/26 | Nights | Omar S. | E-2134A | VI complete. Coating intact |
| 11/11/26 | Nights | Omar S. | E-2106B | VI complete |
| 11/11/26 | Nights | Kendra J. | T-2102 | Internal Visual complete |
| 11/11/26 | Nights | Wes D. | D-2122 | Internal Visual complete. No cracking found |
| 11/11/26 | Nights | Megan F. | E-2102A | VI complete |
| 11/11/26 | Nights | Rusty C. | D-2143 | Internal Visual complete |
| 11/11/26 | Nights | Wes D. | D-2131 | Internal Visual complete |
| 11/11/26 | Nights | Omar S. | D-2194 | Internal Visual complete. No cracking found |
| 11/11/26 | Nights | Rusty C. | E-2103B | VI complete |
| 11/11/26 | Nights | Wes D. | E-2125A | VI complete. Gaskets surfaces good |
| 11/11/26 | Nights | Omar S. | E-2108A | VI complete |
| 11/11/26 | Days | Marcus H. | E-2137A | VI complete |
| 11/11/26 | Days | Marcus H. | E-2115B | VI complete. Light scale, no pitting |
| 11/11/26 | Days | Carla V. | E-2110A | VI complete |
| 11/11/26 | Days | Grant W. | PSV-21300 | PSV Removed complete |
| 11/11/26 | Days | Priya N. | D-2182 | Internal Visual complete |
| 11/11/26 | Days | Grant W. | EA-2106 | VI complete |
| 11/11/26 | Days | Tasha R. | E-2104A | VI complete |
| 11/11/26 | Days | Priya N. | PSV-21312 | PSV Removed complete |
| 11/11/26 | Days | Marcus H. | PSV-21382 | PSV Removed complete |
| 11/11/26 | Days | Luis O. | E-2111A | VI complete. Minor general corrosion, within allowance |
| 11/11/26 | Days | Andre K. | E-2111A | VI complete. No cracking found |
| 11/11/26 | Days | Andre K. | E-2108A | VI complete |
| 11/11/26 | Days | Tasha R. | E-2132A | VI complete. Minor general corrosion, within allowance |
| 11/11/26 | Days | Dwayne P. | H-2101 | Burners complete |
| 11/11/26 | Days | Priya N. | PSV-21330 | PSV Removed complete. No recordable indications |
| 11/11/26 | Days | Hollis B. | D-2164 | Internal Visual complete |
| 11/11/26 | Days | Marcus H. | PSV-21322 | PSV Removed complete |
| 11/11/26 | Days | Carla V. | E-2119A | VI complete |
| 11/11/26 | Days | Carla V. | E-2101A | VI complete |
| 11/11/26 | Days | Priya N. | E-2140A | VI complete. Gaskets surfaces good |
| 11/11/26 | Days | Grant W. | PSV-21328 | PSV Removed complete. Light scale, no pitting |
| 11/11/26 | Days | Priya N. | E-2101A | VI complete |
| 11/11/26 | Days | Hollis B. | E-2129A | VI complete |
| 11/11/26 | Days | Priya N. | D-2140 | Internal Visual complete. Coating intact |
| 11/11/26 | Days | Andre K. | D-2146 | Internal Visual complete |
| 11/11/26 | Days | Carla V. | EA-2108 | VI complete |
| 11/11/26 | Days | Marcus H. | E-2122A | VI complete. Coating intact |
| 11/11/26 | Days | Hollis B. | E-2126A | VI complete |
| 11/11/26 | Days | Grant W. | E-2111A | VI complete |
| 11/11/26 | Days | Grant W. | PSV-21364 | PSV Removed complete |
| 11/11/26 | Days | Hollis B. | PSV-21362 | PSV Removed complete |
| 11/11/26 | Days | Priya N. | E-2115B | VI complete |
| 11/11/26 | Days | Andre K. | E-2116A | VI complete |
| 11/11/26 | Days | Luis O. | E-2140A | VI complete |
| 11/11/26 | Days | Dwayne P. | D-2149 | Internal Visual complete |
| 11/11/26 | Days | Luis O. | E-2118B | VI complete |
| 11/11/26 | Days | Carla V. | T-2103 | Internal Visual complete |
| 11/11/26 | Days | Luis O. | D-2119 | Internal Visual complete. No recordable indications |
| 11/11/26 | Days | Andre K. | E-2106B | VI complete |
| 11/11/26 | Days | Carla V. | PSV-21336 | PSV Removed complete |
| 11/11/26 | Days | Carla V. | E-2115B | VI complete. Minor general corrosion, within allowance |
| 11/11/26 | Days | Andre K. | E-2109B | VI complete |
| 11/11/26 | Days | Carla V. | D-2113 | Internal Visual complete |
| 11/11/26 | Days | Grant W. | 6"-P-2134-A1 | External Visual complete. No cracking found |
| 11/11/26 | Days | Marcus H. | E-2121B | VI complete |
| 11/11/26 | Days | Marcus H. | PSV-21338 | PSV Removed complete |
| 11/11/26 | Days | Grant W. | E-2112B | VI complete |
| 11/11/26 | Days | Marcus H. | E-2106B | VI complete |
| 11/11/26 | Days | Andre K. | D-2173 | Internal Visual complete |
| 11/11/26 | Days | Priya N. | PSV-21334 | PSV Removed complete |
| 11/11/26 | Days | Carla V. | D-2185 | Internal Visual complete. No recordable indications |
| 11/11/26 | Days | Marcus H. | E-2106B | VI complete. Gaskets surfaces good |
| 11/11/26 | Days | Tasha R. | E-2120A | VI complete. Light scale, no pitting |
| 11/11/26 | Days | Marcus H. | E-2118B | VI complete |
| 11/11/26 | Days | Dwayne P. | E-2102A | VI complete |
| 11/11/26 | Days | Andre K. | E-2121B | VI complete. No cracking found |
| 11/11/26 | Days | Andre K. | D-2116 | Internal Visual complete |
| 11/11/26 | Days | Priya N. | E-2102A | VI complete. No cracking found |
| 11/11/26 | Days | Carla V. | E-2115B | VI complete. Minor general corrosion, within allowance |
| 11/11/26 | Days | Hollis B. | PSV-21342 | PSV Removed complete |
| 11/11/26 | Days | Hollis B. | E-2134A | VI complete |
| 11/11/26 | Days | Dwayne P. | E-2134A | VI complete. No recordable indications |
| 11/11/26 | Days | Grant W. | E-2121B | VI complete |
| 11/11/26 | Days | Carla V. | E-2116A | VI complete |
| 11/11/26 | Days | Marcus H. | H-2103 | Burners complete. Light scale, no pitting |
| 11/11/26 | Days | Grant W. | E-2120A | VI complete |
| 11/11/26 | Days | Marcus H. | E-2138A | VI complete |
| 11/11/26 | Days | Carla V. | E-2108A | VI complete |
| 11/11/26 | Days | Carla V. | E-2103B | VI complete |