Exchangers
E-2110A
BEU U-tube
In progress
1 RR · 0 open
Administrative notes
Internal only.
Wallchart — E-2110A
Click a cell to sign it or add a note. A red pill is an RR — click it to open.
1 of 1 items · click a cell to edit, drag a column edge to resize
| Equip # | Equipment Name | Work Order | Description | Progress | Scope | Component | Status | VI | Flanges VI | ECT/RFT/IRIS | UTT | Final QA | Repair Recommendation (RR) | Repair Complete | Comments |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| E-2110A | Steam Generator | WO-48762 | BEU U-tube | Pull bundle, VI all components, IRIS 20% tubes | Channel (Bonnet) | Cleaned | CV 11/11 | OS 11/13 No recordable indications | N/A | In progress. GW 11/22 about half done | ○︎ | · | ○︎ | ○︎ | |
| WO-48762 | Shell | CV 11/12 | MH 11/14 | N/A | In progress. GW 11/22 about half done | ○︎ | RR-017-E-2110A | ○︎ | ○︎ | ||||||
| WO-48762 | Tube Bundle | TR 11/12 No cracking found | MF 11/14 Light scale, no pitting | WD 11/16 Minor general corrosion, within allowance | In progress. GW 11/22 about half done | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48762 | Floating Head | MH 11/12 Coating intact | WD 11/14 Minor general corrosion, within allowance | N/A | Delayed. Insulation not stripped | ○︎ | · | ○︎ | ○︎ |