| Asset type | In scope | Closed out | % | Open RRs |
|---|---|---|---|---|
| Drums | 12 | 12 | 100% | 0 |
| Exchangers | 8 | 8 | 100% | 0 |
| PSV Pull Removed 10/10 (100%) · Installed 10/10 (100%) | 10 | 10 | 100% | 0 |
| Total | 30 | 30 | 100% | 0 |
| Asset type | Written | Closed | Deferred | Open |
|---|---|---|---|---|
| PSV Pull | 2 | 2 | 0 | 0 |
| Drums | 1 | 1 | 0 | 0 |
| Total | 3 | 3 | 0 | 0 |
| RR # | Equipment / package | Asset type | Finding | Written | Status |
|---|---|---|---|---|---|
| RR-018-D-1425 | D-1425 | Drums | IRIS on 20% of tubes found 6 tubes with wall loss over 40% at the inlet end, rows 1 and 2. | 4/21/26 | Repair verified & closed |
| RR-019-PSV-14308 | PSV-14308 | PSV Pull | WFMT found a 1.5 in. linear indication at the toe of the N3 nozzle-to-shell weld. | 4/24/26 | Repair verified & closed |
| RR-020-PSV-14306 | PSV-14306 | PSV Pull | Trays 14 and 15 have two dislodged valve caps and one bent support beam. | 4/27/26 | Repair verified & closed |
| Drums · 12 in scope | ||
|---|---|---|
| D-1410 | Vertical vessel | Closed out |
| D-1413 | Horizontal vessel with boot | Closed out |
| D-1416 | Horizontal vessel with boot | Closed out |
| D-1419 | Vertical vessel | Closed out |
| D-1422 | Horizontal vessel with boot | Closed out |
| D-1425 | Vertical vessel | Closed out |
| D-1428 | Horizontal vessel with boot | Closed out |
| D-1431 | Horizontal vessel with boot | Closed out |
| D-1434 | Horizontal vessel | Closed out |
| D-1437 | Horizontal vessel with boot | Closed out |
| D-1440 | Horizontal vessel | Closed out |
| Exchangers · 8 in scope | ||
|---|---|---|
| E-1401A | AES shell and tube | Closed out |
| E-1402A | BEU U-tube | Closed out |
| E-1403B | AEL fixed tubesheet | Closed out |
| E-1404A | BEU U-tube | Closed out |
| E-1405A | AES shell and tube | Closed out |
| E-1406B | BEU U-tube | Closed out |
| E-1407A | AEL fixed tubesheet | Closed out |
| E-1408A | BEU U-tube | Closed out |
| PSV Pull · 10 in scope | ||
|---|---|---|
| PSV-14300 | Overhead Accumulator | Closed out |
| PSV-14302 | Fuel Gas KO | Closed out |
| PSV-14304 | Steam Header | Closed out |
| PSV-14306 | Exchanger Shell Side | Closed out |
| PSV-14308 | Pump Discharge | Closed out |
| PSV-14310 | Flash Drum | Closed out |
| PSV-14312 | Reboiler Outlet | Closed out |
| PSV-14314 | Tower Overhead | Closed out |
| PSV-14316 | Overhead Accumulator | Closed out |
| PSV-14318 | Fuel Gas KO | Closed out |
| Date | Shift | Inspector | Equipment | Details |
|---|---|---|---|---|
| 5/7/26 | Nights | Wes D. | E-1403B | Final QA complete |
| 5/7/26 | Nights | Omar S. | E-1401A | Final QA complete |
| 5/7/26 | Nights | Omar S. | PSV-14302 | PSV Installed complete. Light scale, no pitting |
| 5/7/26 | Nights | Rusty C. | E-1403B | Final QA complete |
| 5/7/26 | Nights | Megan F. | PSV-14306 | PSV Installed complete |
| 5/7/26 | Nights | Omar S. | E-1408A | Final QA complete |
| 5/7/26 | Nights | Kendra J. | E-1403B | Final QA complete |
| 5/7/26 | Days |
| D-1443 | Horizontal vessel with boot | Closed out |
| Tasha R. |
| D-1419 |
| Final QA complete |
| 5/7/26 | Days | Tasha R. | E-1404A | Final QA complete |
| 5/7/26 | Days | Andre K. | E-1407A | Final QA complete |
| 5/7/26 | Days | Priya N. | PSV-14304 | PSV Installed complete. No recordable indications |
| 5/6/26 | Nights | Kendra J. | E-1408A | Final QA complete |
| 5/6/26 | Nights | Megan F. | E-1402A | Final QA complete |
| 5/6/26 | Nights | Rusty C. | E-1407A | Final QA complete |
| 5/6/26 | Nights | Omar S. | PSV-14314 | PSV Installed complete |
| 5/6/26 | Days | Hollis B. | E-1408A | Final QA complete |
| 5/6/26 | Days | Tasha R. | E-1405A | Final QA complete |
| 5/6/26 | Days | Carla V. | E-1404A | Final QA complete |
| 5/6/26 | Days | Marcus H. | E-1404A | Final QA complete |
| 5/6/26 | Days | Grant W. | E-1402A | Final QA complete |
| 5/6/26 | Days | Dwayne P. | E-1402A | Final QA complete |
| 5/6/26 | Days | Carla V. | E-1401A | Final QA complete |
| 5/6/26 | Days | Priya N. | D-1440 | Final QA complete |
| 5/6/26 | Days | Dwayne P. | D-1425 | Final QA complete |
| 5/6/26 | Days | Hollis B. | D-1443 | Final QA complete |
| 5/5/26 | Nights | Omar S. | E-1405A | Final QA complete |
| 5/5/26 | Nights | Wes D. | PSV-14308 | PSV Installed complete. Minor general corrosion, within allowance |
| 5/5/26 | Nights | Wes D. | D-1431 | Final QA complete |
| 5/5/26 | Days | Luis O. | PSV-14318 | PSV Installed complete. Gaskets surfaces good |
| 5/5/26 | Days | Marcus H. | D-1434 | Final QA complete |
| 5/5/26 | Days | Priya N. | D-1413 | Final QA complete |
| 5/5/26 | Days | Grant W. | E-1405A | Final QA complete |
| 5/5/26 | Days | Dwayne P. | E-1407A | Final QA complete |
| 5/5/26 | Days | Hollis B. | D-1428 | Final QA complete |
| 5/5/26 | Days | Andre K. | E-1403B | Final QA complete |
| 5/5/26 | Days | Andre K. | E-1407A | Final QA complete |
| 5/5/26 | Days | Dwayne P. | PSV-14310 | PSV Installed complete |
| 5/5/26 | Days | Andre K. | E-1406B | Final QA complete |
| 5/4/26 | Nights | Megan F. | D-1410 | Final QA complete |
| 5/4/26 | Days | Hollis B. | D-1416 | Final QA complete |
| 5/4/26 | Days | Tasha R. | E-1406B | Final QA complete |
| 5/4/26 | Days | Luis O. | PSV-14316 | PSV Installed complete. Minor general corrosion, within allowance |
| 5/4/26 | Days | Grant W. | D-1437 | Final QA complete |
| 5/4/26 | Days | Marcus H. | E-1401A | Final QA complete |
| 5/3/26 | Nights | Megan F. | PSV-14300 | PSV Installed complete |
| 5/3/26 | Nights | Kendra J. | E-1404A | Final QA complete |
| 5/3/26 | Days | Marcus H. | PSV-14312 | PSV Installed complete |
| 5/3/26 | Days | Marcus H. | E-1402A | Final QA complete |
| 5/3/26 | Days | Andre K. | E-1408A | Final QA complete |
| 5/3/26 | Days | Dwayne P. | E-1405A | Final QA complete |
| 5/3/26 | Days | Tasha R. | D-1422 | Final QA complete |
| 5/3/26 | Days | Marcus H. | D-1428 | Flanges VI complete |
| 5/3/26 | Days | Grant W. | E-1406B | Final QA complete |
| 5/3/26 | Days | Hollis B. | E-1406B | Final QA complete |
| 5/3/26 | Days | Carla V. | E-1401A | Final QA complete |
| 5/2/26 | Nights | Kendra J. | E-1405A | UTT complete. Light scale, no pitting |
| 5/2/26 | Nights | Megan F. | D-1425 | Flanges VI complete. No recordable indications |
| 5/2/26 | Days | Marcus H. | D-1434 | Flanges VI complete |
| 5/2/26 | Days | Priya N. | E-1407A | UTT complete. Gaskets surfaces good |
| 5/2/26 | Days | Luis O. | E-1404A | UTT complete. Light scale, no pitting |
| 5/2/26 | Days | Marcus H. | D-1440 | Flanges VI complete. Minor general corrosion, within allowance |
| 5/1/26 | Nights | Wes D. | E-1404A | UTT complete |
| 5/1/26 | Nights | Megan F. | E-1404A | UTT complete |
| 5/1/26 | Days | Andre K. | D-1416 | Flanges VI complete. Light scale, no pitting |
| 5/1/26 | Days | Priya N. | E-1407A | UTT complete. Light scale, no pitting |
| 5/1/26 | Days | Tasha R. | PSV-14316 | Outlet Piping VT complete. No cracking found |
| 5/1/26 | Days | Luis O. | E-1408A | UTT complete |
| 5/1/26 | Days | Tasha R. | E-1402A | UTT complete. No cracking found |
| 4/30/26 | Nights | Omar S. | D-1437 | Flanges VI complete |
| 4/30/26 | Nights | Wes D. | D-1419 | Flanges VI complete. Light scale, no pitting |
| 4/30/26 | Nights | Kendra J. | PSV-14306 | Outlet Piping VT complete |
| 4/30/26 | Days | Tasha R. | D-1413 | Flanges VI complete |
| 4/30/26 | Days | Andre K. | E-1408A | UTT complete. Gaskets surfaces good |
| 4/30/26 | Days | Andre K. | PSV-14314 | Outlet Piping VT complete |
| 4/30/26 | Days | Andre K. | E-1403B | UTT complete |
| 4/30/26 | Days | Priya N. | D-1410 | Flanges VI complete. Light scale, no pitting |
| 4/30/26 | Days | Luis O. | D-1431 | Flanges VI complete |
| 4/30/26 | Days | Tasha R. | PSV-14310 | Outlet Piping VT complete |
| 4/30/26 | Days | Andre K. | E-1404A | UTT complete |
| 4/30/26 | Days | Marcus H. | E-1401A | UTT complete. No cracking found |
| 4/30/26 | Days | Priya N. | E-1408A | UTT complete |
| 4/30/26 | Days | Hollis B. | E-1405A | UTT complete |
| 4/30/26 | Days | Luis O. | D-1422 | Flanges VI complete |
| 4/30/26 | Days | Andre K. | E-1401A | UTT complete. Light scale, no pitting |
| 4/29/26 | Nights | Kendra J. | E-1401A | UTT complete |
| 4/29/26 | Nights | Megan F. | E-1406B | UTT complete. No cracking found |
| 4/29/26 | Nights | Omar S. | E-1401A | UTT complete. No cracking found |
| 4/29/26 | Nights | Rusty C. | E-1402A | UTT complete |
| 4/29/26 | Nights | Megan F. | PSV-14302 | Outlet Piping VT complete. Light scale, no pitting |
| 4/29/26 | Days | Grant W. | D-1443 | Flanges VI complete |
| 4/29/26 | Days | Luis O. | E-1402A | UTT complete |
| 4/29/26 | Days | Grant W. | E-1403B | UTT complete. Minor general corrosion, within allowance |
| 4/28/26 | Nights | Omar S. | D-1434 | WFMT complete. No recordable indications |
| 4/28/26 | Nights | Megan F. | E-1406B | UTT complete |
| 4/28/26 | Nights | Omar S. | D-1413 | WFMT complete |
| 4/28/26 | Nights | Omar S. | E-1402A | UTT complete |
| 4/28/26 | Nights | Wes D. | E-1403B | UTT complete. Minor general corrosion, within allowance |
| 4/28/26 | Days | Priya N. | E-1408A | UTT complete |
| 4/28/26 | Days | Tasha R. | D-1428 | WFMT complete. Gaskets surfaces good |
| 4/28/26 | Days | Tasha R. | E-1405A | UTT complete |
| 4/28/26 | Days | Priya N. | D-1422 | WFMT complete |
| 4/28/26 | Days | Marcus H. | E-1406B | UTT complete |
| 4/28/26 | Days | Luis O. | D-1419 | WFMT complete. Coating intact |
| 4/28/26 | Days | Carla V. | E-1403B | UTT complete. No recordable indications |
| 4/28/26 | Days | Luis O. | E-1407A | UTT complete. Coating intact |
| 4/27/26 | Nights | Rusty C. | E-1407A | UTT complete |
| 4/27/26 | Nights | Megan F. | PSV-14300 | Outlet Piping VT complete. Minor general corrosion, within allowance |
| 4/27/26 | Days | Priya N. | E-1406B | UTT complete |
| 4/27/26 | Days | Carla V. | D-1410 | WFMT complete |
| 4/27/26 | Days | Priya N. | E-1405A | UTT complete |
| 4/27/26 | Days | Carla V. | PSV-14308 | Outlet Piping VT complete. No cracking found |
| 4/27/26 | Days | Dwayne P. | E-1401A | ECT/RFT/IRIS complete |
| 4/26/26 | Nights | Wes D. | D-1431 | WFMT complete |
| 4/26/26 | Nights | Omar S. | PSV-14312 | Outlet Piping VT complete. Coating intact |
| 4/26/26 | Days | Andre K. | D-1437 | WFMT complete |
| 4/26/26 | Days | Tasha R. | E-1406B | ECT/RFT/IRIS complete. Gaskets surfaces good |
| 4/26/26 | Days | Tasha R. | D-1416 | WFMT complete |
| 4/25/26 | Nights | Wes D. | E-1403B | ECT/RFT/IRIS complete |
| 4/25/26 | Days | Andre K. | D-1440 | WFMT complete. Minor general corrosion, within allowance |
| 4/25/26 | Days | Carla V. | E-1405A | ECT/RFT/IRIS complete. Coating intact |
| 4/25/26 | Days | Grant W. | PSV-14318 | Outlet Piping VT complete |
| 4/25/26 | Days | Priya N. | D-1425 | WFMT complete |
| 4/25/26 | Days | Dwayne P. | E-1402A | ECT/RFT/IRIS complete |
| 4/25/26 | Days | Hollis B. | D-1443 | WFMT complete. No cracking found |
| 4/25/26 | Days | Luis O. | PSV-14304 | Outlet Piping VT complete |
| 4/24/26 | Nights | Omar S. | D-1437 | UTT complete |
| 4/24/26 | Nights | Kendra J. | PSV-14314 | Inlet Piping VT complete. No cracking found |
| 4/24/26 | Days | Hollis B. | D-1410 | UTT complete. Gaskets surfaces good |
| 4/24/26 | Days | Grant W. | E-1404A | ECT/RFT/IRIS complete |
| 4/24/26 | Days | Grant W. | D-1443 | UTT complete. No recordable indications |
| 4/24/26 | Days | Marcus H. | E-1408A | ECT/RFT/IRIS complete |
| 4/23/26 | Days | Grant W. | D-1413 | UTT complete. Coating intact |
| 4/23/26 | Days | Andre K. | D-1422 | UTT complete |
| 4/23/26 | Days | Andre K. | D-1416 | UTT complete. Light scale, no pitting |
| 4/23/26 | Days | Dwayne P. | PSV-14318 | Inlet Piping VT complete |
| 4/22/26 | Nights | Wes D. | PSV-14316 | Inlet Piping VT complete |
| 4/22/26 | Nights | Omar S. | E-1405A | Flanges VI complete |
| 4/22/26 | Nights | Kendra J. | E-1407A | ECT/RFT/IRIS complete. Minor general corrosion, within allowance |
| 4/22/26 | Nights | Wes D. | E-1402A | Flanges VI complete |
| 4/22/26 | Nights | Kendra J. | D-1431 | UTT complete. No recordable indications |
| 4/22/26 | Days | Luis O. | PSV-14304 | Inlet Piping VT complete. Gaskets surfaces good |
| 4/22/26 | Days | Tasha R. | PSV-14312 | Inlet Piping VT complete |
| 4/22/26 | Days | Marcus H. | D-1425 | UTT complete |
| 4/21/26 | Nights | Kendra J. | E-1406B | Flanges VI complete. Coating intact |
| 4/21/26 | Nights | Omar S. | E-1407A | Flanges VI complete. Gaskets surfaces good |
| 4/21/26 | Nights | Megan F. | E-1406B | Flanges VI complete |
| 4/21/26 | Days | Dwayne P. | PSV-14306 | Inlet Piping VT complete |
| 4/21/26 | Days | Hollis B. | D-1428 | UTT complete |
| 4/21/26 | Days | Dwayne P. | E-1402A | Flanges VI complete |
| 4/21/26 | Days | Tasha R. | D-1434 | UTT complete |
| 4/21/26 | Days | Luis O. | PSV-14308 | Inlet Piping VT complete |
| 4/21/26 | Days | Priya N. | E-1404A | Flanges VI complete |
| 4/20/26 | Nights | Kendra J. | E-1406B | Flanges VI complete |
| 4/20/26 | Nights | Rusty C. | E-1404A | Flanges VI complete |
| 4/20/26 | Nights | Rusty C. | D-1428 | External Visual complete |
| 4/20/26 | Days | Tasha R. | E-1403B | Flanges VI complete |
| 4/20/26 | Days | Dwayne P. | D-1440 | UTT complete. Gaskets surfaces good |
| 4/20/26 | Days | Carla V. | E-1405A | Flanges VI complete. Light scale, no pitting |
| 4/20/26 | Days | Tasha R. | D-1419 | UTT complete |
| 4/20/26 | Days | Hollis B. | D-1434 | External Visual complete. Minor general corrosion, within allowance |
| 4/19/26 | Nights | Omar S. | E-1408A | Flanges VI complete |
| 4/19/26 | Nights | Rusty C. | PSV-14302 | Inlet Piping VT complete |
| 4/19/26 | Days | Andre K. | D-1410 | External Visual complete. Gaskets surfaces good |
| 4/19/26 | Days | Carla V. | E-1401A | Flanges VI complete. Light scale, no pitting |
| 4/19/26 | Days | Luis O. | D-1413 | External Visual complete. Gaskets surfaces good |
| 4/19/26 | Days | Grant W. | E-1401A | Flanges VI complete. Coating intact |
| 4/19/26 | Days | Dwayne P. | E-1407A | Flanges VI complete |
| 4/19/26 | Days | Carla V. | E-1408A | Flanges VI complete |
| 4/19/26 | Days | Tasha R. | E-1404A | Flanges VI complete |
| 4/19/26 | Days | Luis O. | E-1405A | Flanges VI complete |
| 4/19/26 | Days | Priya N. | E-1408A | Flanges VI complete |
| 4/19/26 | Days | Priya N. | PSV-14310 | Inlet Piping VT complete. Light scale, no pitting |
| 4/19/26 | Days | Marcus H. | E-1401A | Flanges VI complete |
| 4/19/26 | Days | Marcus H. | E-1408A | Flanges VI complete |
| 4/18/26 | Nights | Omar S. | E-1401A | Flanges VI complete |
| 4/18/26 | Nights | Kendra J. | E-1407A | Flanges VI complete |
| 4/18/26 | Nights | Kendra J. | PSV-14314 | PSV Removed complete. Minor general corrosion, within allowance |
| 4/18/26 | Nights | Omar S. | E-1407A | Flanges VI complete. Minor general corrosion, within allowance |
| 4/18/26 | Nights | Megan F. | D-1425 | External Visual complete |
| 4/18/26 | Days | Andre K. | PSV-14300 | Inlet Piping VT complete |
| 4/18/26 | Days | Marcus H. | PSV-14308 | PSV Removed complete |
| 4/18/26 | Days | Tasha R. | E-1404A | Flanges VI complete. Coating intact |
| 4/18/26 | Days | Tasha R. | E-1403B | Flanges VI complete |
| 4/18/26 | Days | Grant W. | D-1437 | External Visual complete |
| 4/18/26 | Days | Tasha R. | D-1416 | External Visual complete |
| 4/17/26 | Nights | Rusty C. | D-1443 | External Visual complete |
| 4/17/26 | Nights | Wes D. | D-1440 | External Visual complete. Light scale, no pitting |
| 4/17/26 | Nights | Omar S. | E-1407A | VI complete. No cracking found |
| 4/17/26 | Nights | Omar S. | E-1403B | Flanges VI complete |
| 4/17/26 | Days | Luis O. | E-1405A | Flanges VI complete. Coating intact |
| 4/17/26 | Days | Carla V. | PSV-14318 | PSV Removed complete |
| 4/17/26 | Days | Priya N. | E-1403B | Flanges VI complete |
| 4/17/26 | Days | Marcus H. | E-1402A | Flanges VI complete. No recordable indications |
| 4/17/26 | Days | Grant W. | D-1431 | External Visual complete |
| 4/17/26 | Days | Andre K. | E-1406B | Flanges VI complete. Light scale, no pitting |
| 4/17/26 | Days | Carla V. | PSV-14300 | PSV Removed complete. Gaskets surfaces good |
| 4/17/26 | Days | Andre K. | D-1419 | External Visual complete |
| 4/17/26 | Days | Tasha R. | E-1402A | Flanges VI complete |
| 4/16/26 | Nights | Megan F. | E-1403B | VI complete |
| 4/16/26 | Nights | Kendra J. | E-1401A | VI complete. Minor general corrosion, within allowance |
| 4/16/26 | Nights | Wes D. | E-1402A | VI complete. Coating intact |
| 4/16/26 | Nights | Kendra J. | E-1408A | VI complete. Light scale, no pitting |
| 4/16/26 | Nights | Rusty C. | E-1401A | VI complete |
| 4/16/26 | Nights | Wes D. | PSV-14304 | PSV Removed complete |
| 4/16/26 | Days | Carla V. | E-1407A | VI complete |
| 4/16/26 | Days | Tasha R. | E-1404A | VI complete |
| 4/16/26 | Days | Tasha R. | D-1410 | Internal Visual complete |
| 4/16/26 | Days | Luis O. | E-1406B | VI complete |
| 4/16/26 | Days | Luis O. | D-1422 | External Visual complete |
| 4/16/26 | Days | Luis O. | D-1413 | Internal Visual complete |
| 4/16/26 | Days | Dwayne P. | E-1407A | VI complete |
| 4/15/26 | Nights | Megan F. | PSV-14310 | PSV Removed complete |
| 4/15/26 | Nights | Rusty C. | D-1443 | Internal Visual complete. No recordable indications |
| 4/15/26 | Nights | Rusty C. | D-1431 | Internal Visual complete |
| 4/15/26 | Days | Carla V. | E-1405A | VI complete. Gaskets surfaces good |
| 4/15/26 | Days | Marcus H. | E-1408A | VI complete |
| 4/15/26 | Days | Marcus H. | E-1402A | VI complete |
| 4/15/26 | Days | Hollis B. | E-1404A | VI complete |
| 4/15/26 | Days | Luis O. | D-1422 | Internal Visual complete |
| 4/15/26 | Days | Hollis B. | D-1440 | Internal Visual complete |
| 4/15/26 | Days | Dwayne P. | E-1406B | VI complete |
| 4/15/26 | Days | Dwayne P. | D-1437 | Internal Visual complete. Light scale, no pitting |
| 4/15/26 | Days | Dwayne P. | E-1401A | VI complete |
| 4/15/26 | Days | Priya N. | E-1405A | VI complete |
| 4/15/26 | Days | Tasha R. | D-1425 | Internal Visual complete. Minor general corrosion, within allowance |
| 4/15/26 | Days | Marcus H. | E-1402A | VI complete |
| 4/15/26 | Days | Tasha R. | E-1408A | VI complete |
| 4/14/26 | Nights | Rusty C. | E-1402A | VI complete |
| 4/14/26 | Nights | Kendra J. | D-1419 | Internal Visual complete |
| 4/14/26 | Nights | Omar S. | E-1405A | VI complete. No recordable indications |
| 4/14/26 | Nights | Megan F. | E-1406B | VI complete |
| 4/14/26 | Days | Carla V. | D-1434 | Internal Visual complete |
| 4/14/26 | Days | Hollis B. | PSV-14302 | PSV Removed complete. Coating intact |
| 4/13/26 | Nights | Rusty C. | E-1404A | VI complete |
| 4/13/26 | Nights | Rusty C. | E-1403B | VI complete. Light scale, no pitting |
| 4/13/26 | Days | Dwayne P. | E-1405A | VI complete |
| 4/13/26 | Days | Tasha R. | D-1416 | Internal Visual complete. Gaskets surfaces good |
| 4/13/26 | Days | Grant W. | E-1403B | VI complete. Gaskets surfaces good |
| 4/13/26 | Days | Dwayne P. | E-1401A | VI complete |
| 4/12/26 | Nights | Kendra J. | PSV-14306 | PSV Removed complete. No recordable indications |
| 4/12/26 | Nights | Kendra J. | E-1407A | VI complete |
| 4/12/26 | Nights | Omar S. | PSV-14316 | PSV Removed complete. No cracking found |
| 4/12/26 | Days | Dwayne P. | E-1404A | VI complete |
| 4/12/26 | Days | Marcus H. | PSV-14312 | PSV Removed complete |
| 4/12/26 | Days | Andre K. | E-1403B | VI complete |
| 4/12/26 | Days | Tasha R. | E-1406B | VI complete |
| 4/12/26 | Days | Marcus H. | D-1428 | Internal Visual complete. No cracking found |
| 4/12/26 | Days | Dwayne P. | E-1408A | VI complete. Minor general corrosion, within allowance |