Asset type
PSV Pull
50 in scope · 4 complete · 1 open RR
1 column hidden on this screen
50 of 50 items · click a cell to edit, drag a column edge to resize
| PSV # | Service | Progress | Set Pressure | PSV Removed | Inlet Piping VT | Outlet Piping VT | PSV Installed |
|---|---|---|---|---|---|---|---|
| PSV-21300 | Overhead Accumulator | 50 psig | GW 11/11 | KJ 11/13 | In progress. TR 11/22 about half done | ○︎ | |
| PSV-21302 | Fuel Gas KO | 150 psig | In progress. DP 11/22 readings in progress | ○︎ | ○︎ | ○︎ | |
| PSV-21304 | Steam Header | 165 psig | DP 11/12 No cracking found | AK 11/14 | In progress. RC 11/22 about half done | ○︎ | |
| PSV-21306 | Exchanger Shell Side | 165 psig | In progress. DP 11/22 top half complete | ○︎ | ○︎ | ○︎ | |
| PSV-21308 | Pump Discharge | 75 psig | In progress. DP 11/22 started, scaffold up | ○︎ | ○︎ | ○︎ | |
| Rendering 45 more… | |||||||