| Equip # | Equipment Name | Work Order | Description | Progress | Scope | Component | Status | VI | Flanges VI | ECT/RFT/IRIS | UTT | Final QA | Repair Recommendation (RR) | Repair Complete | Comments |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| E-2121B | Crude / Diesel Exchanger | WO-48566 | BEU U-tube | Pull bundle, VI all components, IRIS 20% tubes | Channel (Bonnet) | Ready for inspection | GW 11/11 | WD 11/15 | N/A | In progress. MF 11/22 about half done | ○︎ | · | ○︎ | ○︎ | |
| WO-48566 | Shell | MH 11/11 | WD 11/14 | N/A | In progress. MF 11/22 started, scaffold up | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48566 | Tube Bundle | AK 11/11 No cracking found | PN 11/14 Gaskets surfaces good | WD 11/16 Light scale, no pitting | Delayed. Waiting on hydroblast cleaning | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48566 | Floating Head | DP 11/12 Gaskets surfaces good | OS 11/13 Gaskets surfaces good | N/A | In progress. MF 11/22 started, scaffold up | ○︎ | · | ○︎ | ○︎ |