Exchangers
E-2106B
AEL fixed tubesheet
Discovery delayedIn progress
0 RRs · 0 open
Administrative notes
Internal only.
Wallchart — E-2106B
Click a cell to sign it or add a note. A red pill is an RR — click it to open.
1 of 1 items · click a cell to edit, drag a column edge to resize
| Equip # | Equipment Name | Work Order | Description | Progress | Scope | Component | Status | VI | Flanges VI | ECT/RFT/IRIS | UTT | Final QA | Repair Recommendation (RR) | Repair Complete | Comments |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| E-2106B | Trim Cooler | WO-48923 | AEL fixed tubesheet | Pull bundle, VI all components, IRIS 20% tubes | Channel (Bonnet) | Ready for inspection | OS 11/11 | Delayed. Waiting on hydroblast cleaning | N/A | ○︎ | ○︎ | · | ○︎ | ○︎ | |
| WO-48923 | Shell | MH 11/11 Gaskets surfaces good | Delayed. Unit not released by operations | N/A | ○︎ | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48923 | Tube Bundle | MH 11/11 | Delayed. Insulation not stripped | ● | ○︎ | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48923 | Floating Head | AK 11/11 | In progress. MF 11/22 started, scaffold up | N/A | ○︎ | ○︎ | · | ○︎ | ○︎ |