Exchangers
E-2103B
BEU U-tube
In progress
1 RR · 1 open
Administrative notes
Internal only.
Wallchart — E-2103B
Click a cell to sign it or add a note. A red pill is an RR — click it to open.
1 of 1 items · click a cell to edit, drag a column edge to resize
| Equip # | Equipment Name | Work Order | Description | Progress | Scope | Component | Status | VI | Flanges VI | ECT/RFT/IRIS | UTT | Final QA | Repair Recommendation (RR) | Repair Complete | Comments |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| E-2103B | Kero Pumparound Cooler | WO-48798 | BEU U-tube | 1 open RR | Pull bundle, VI all components, IRIS 20% tubes | Channel (Bonnet) | Inspection complete | RC 11/11 | LO 11/13 | N/A | In progress. HB 11/22 top half complete | ○︎ | · | ○︎ | ○︎ |
| WO-48798 | Shell | DP 11/12 No recordable indications | TR 11/14 | N/A | Delayed. Insulation not stripped | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48798 | Tube Bundle | CV 11/11 | LO 11/13 | DP 11/15 | In progress. MF 11/22 readings in progress | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48798 | Floating Head | MH 11/12 No cracking found | WD 11/14 No cracking found | N/A | Delayed. Insulation not stripped | ○︎ | RR-010-E-2103B | ○︎ | ○︎ |