Exchangers
E-2109B
AEL fixed tubesheet
Discovery in progressRepair
1 RR · 0 open
Administrative notes
Internal only.
Wallchart — E-2109B
Click a cell to sign it or add a note. A red pill is an RR — click it to open.
1 of 1 items · click a cell to edit, drag a column edge to resize
| Equip # | Equipment Name | Work Order | Description | Progress | Scope | Component | Status | VI | Flanges VI | ECT/RFT/IRIS | UTT | Final QA | Repair Recommendation (RR) | Repair Complete | Comments |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| E-2109B | Desalter Preheat | WO-48622 | AEL fixed tubesheet | Pull bundle, VI all components, IRIS 20% tubes | Channel (Bonnet) | Inspection complete | AK 11/11 | In progress. OS 11/22 about half done | N/A | ○︎ | ○︎ | RR-008-E-2109B | ○︎ | ○︎ | |
| WO-48622 | Shell | WD 11/11 No cracking found | In progress. MH 11/22 top half complete | N/A | ○︎ | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48622 | Tube Bundle | RC 11/12 | In progress. DP 11/22 readings in progress | ● | ○︎ | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48622 | Floating Head | OS 11/12 | In progress. MF 11/22 readings in progress | N/A | ○︎ | ○︎ | · | ○︎ | ○︎ |