Exchangers
E-2138A
AEL fixed tubesheet
In progress
0 RRs · 0 open
Administrative notes
Internal only.
Wallchart — E-2138A
Click a cell to sign it or add a note. A red pill is an RR — click it to open.
1 of 1 items · click a cell to edit, drag a column edge to resize
| Equip # | Equipment Name | Work Order | Description | Progress | Scope | Component | Status | VI | Flanges VI | ECT/RFT/IRIS | UTT | Final QA | Repair Recommendation (RR) | Repair Complete | Comments |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| E-2138A | Naphtha Cooler | WO-48465 | AEL fixed tubesheet | Pull bundle, VI all components, IRIS 20% tubes | Channel (Bonnet) | Ready for inspection | DP 11/13 | WD 11/14 | N/A | MH 11/18 Minor general corrosion, within allowance | In progress. CV 11/22 started, scaffold up | · | ○︎ | ○︎ | |
| WO-48465 | Shell | MH 11/11 | TR 11/13 Light scale, no pitting | N/A | CV 11/19 | In progress. HB 11/22 about half done | · | ○︎ | ○︎ | ||||||
| WO-48465 | Tube Bundle | OS 11/13 | DP 11/15 | TR 11/17 | TR 11/18 | In progress. RC 11/22 readings in progress | · | ○︎ | ○︎ | ||||||
| WO-48465 | Floating Head | PN 11/13 Light scale, no pitting | OS 11/13 | N/A | LO 11/18 | Delayed. Unit not released by operations | · | ○︎ | ○︎ |