Exchangers
E-2101A
AES shell and tube
In progress
0 RRs · 0 open
Administrative notes
Internal only.
Wallchart — E-2101A
Click a cell to sign it or add a note. A red pill is an RR — click it to open.
1 of 1 items · click a cell to edit, drag a column edge to resize
| Equip # | Equipment Name | Work Order | Description | Progress | Scope | Component | Status | VI | Flanges VI | ECT/RFT/IRIS | UTT | Final QA | Repair Recommendation (RR) | Repair Complete | Comments |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| E-2101A | Crude / Diesel Exchanger | WO-48394 | AES shell and tube | Pull bundle, VI all components, IRIS 20% tubes | Channel (Bonnet) | Inspection complete | AK 11/12 | HB 11/14 | N/A | Delayed. Waiting on scaffold | ○︎ | · | ○︎ | ○︎ | |
| WO-48394 | Shell | WD 11/12 | WD 11/14 | N/A | In progress. LO 11/22 started, scaffold up | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48394 | Tube Bundle | CV 11/11 | HB 11/14 | HB 11/14 | Delayed. Waiting on hydroblast cleaning | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48394 | Floating Head | PN 11/11 | HB 11/14 | N/A | In progress. MH 11/22 about half done | ○︎ | · | ○︎ | ○︎ |