Exchangers
E-2139B
BEU U-tube
Discovery delayedIn progress
0 RRs · 0 open
Administrative notes
Internal only.
Wallchart — E-2139B
Click a cell to sign it or add a note. A red pill is an RR — click it to open.
1 of 1 items · click a cell to edit, drag a column edge to resize
| Equip # | Equipment Name | Work Order | Description | Progress | Scope | Component | Status | VI | Flanges VI | ECT/RFT/IRIS | UTT | Final QA | Repair Recommendation (RR) | Repair Complete | Comments |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| E-2139B | Desalter Preheat | WO-48786 | BEU U-tube | Pull bundle, VI all components, IRIS 20% tubes | Channel (Bonnet) | Inspection complete | MF 11/12 Minor general corrosion, within allowance | In progress. LO 11/22 started, scaffold up | N/A | ○︎ | ○︎ | · | ○︎ | ○︎ | |
| WO-48786 | Shell | MF 11/11 No cracking found | Delayed. Bundle not pulled yet | N/A | ○︎ | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48786 | Tube Bundle | KJ 11/12 Minor general corrosion, within allowance | In progress. KJ 11/22 top half complete | ● | ○︎ | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48786 | Floating Head | OS 11/11 | Delayed. Waiting on hydroblast cleaning | N/A | ○︎ | ○︎ | · | ○︎ | ○︎ |