Exchangers
E-2118B
BEU U-tube
Discovery delayedIn progress
1 RR · 0 open
Administrative notes
Internal only.
Wallchart — E-2118B
Click a cell to sign it or add a note. A red pill is an RR — click it to open.
1 of 1 items · click a cell to edit, drag a column edge to resize
| Equip # | Equipment Name | Work Order | Description | Progress | Scope | Component | Status | VI | Flanges VI | ECT/RFT/IRIS | UTT | Final QA | Repair Recommendation (RR) | Repair Complete | Comments |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| E-2118B | Naphtha Cooler | WO-48232 | BEU U-tube | Pull bundle, VI all components, IRIS 20% tubes | Channel (Bonnet) | Cleaned | KJ 11/11 Gaskets surfaces good | In progress. CV 11/22 started, scaffold up | N/A | ○︎ | ○︎ | · | ○︎ | ○︎ | |
| WO-48232 | Shell | KJ 11/11 | Delayed. Insulation not stripped | N/A | ○︎ | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48232 | Tube Bundle | LO 11/11 | Delayed. Waiting on scaffold | ● | ○︎ | ○︎ | · | ○︎ | ○︎ | ||||||
| WO-48232 | Floating Head | MH 11/11 | In progress. AK 11/22 about half done | N/A | ○︎ | ○︎ | RR-001-E-2118B | RT 11/16 | ○︎ |